Search

CN-114961278-B - Corridor hoisting and integral hoisting method under condition of no interest space

CN114961278BCN 114961278 BCN114961278 BCN 114961278BCN-114961278-B

Abstract

The invention discloses an overall lifting method of a corridor under an unfavorable space condition, which comprises the steps of firstly dividing the corridor into a plurality of sections according to an overall design structure of the corridor, secondly assembling the corridor from two ends to the middle in sequence, assembling the corridor to an unfavorable space position, at least two sections of the corridor to be assembled, then lifting the corridor close to the unfavorable space position by adopting the overall lifting method of the corridor under the unfavorable space condition, and finally lifting a main body of the corridor of the rest sections. The narrow and small space in scene of this scheme make full use of solves the vestibule and assembles, hoist and mount, lower suspension pole installation etc. to guarantee going on smoothly of vestibule hoist and mount, the project that effectual reduction project should place environmental problem lead to the time limit for a project, personnel can not the rational utilization problem, reduce the high altitude simultaneously and assemble the safe risk that brings. The integral sectional hoisting mode has the advantages of higher operation efficiency, more reasonable space application and time application, high installation speed, shortened construction period, convenient installation of workers and safer construction process.

Inventors

  • GAO YUJIE
  • FU QIANG
  • LIN HAO

Assignees

  • 上海宝冶冶金工程有限公司
  • 上海宝冶集团有限公司

Dates

Publication Date
20260508
Application Date
20220408

Claims (7)

  1. 1. The corridor hoisting method under the condition of no space is characterized by comprising the following steps: Step 1, calculating the size of units assembled by the corridor according to the field space conditions; step 2, a third crane is arranged at the far end of the corridor installation section in advance; step 3, sectional assembling the main body of the corridor on the adjacent open ground; Step 4, integrally lifting and shifting the corridor main body to a position below the target position by using a first crane and a second crane, suspending the corridor main body at a certain height from the ground, and lifting the far end of the corridor main body by using a preset third crane; Step 5, installing a lower suspension rod; Step 6, after the installation of the lower suspension rod is completed, the far end of the corridor main body is lifted, and the near end is landed; Step 7, installing a mounting bracket at the proximal end of the corridor main body; Step 8, hoisting the proximal end of the corridor main body by using a first crane, and hoisting equipment at two ends simultaneously until the corridor main body reaches an installation position; And 9, adjusting the corridor main body to a specified position and then fixing.
  2. 2. The method for lifting the corridor under the condition of no space utilization as claimed in claim 1, wherein the suspended height of the main corridor body in the step 4 is larger than the assembly height of the lower suspension rod.
  3. 3. The method for lifting the corridor under the condition of no space utilization as claimed in claim 1, wherein the step 5 is characterized in that the manual hoist is adopted for assembly.
  4. 4. The method for lifting the corridor under the condition of no space utilization according to claim 1, wherein after the lower suspension rod is assembled, the lifting height is adjusted to span the site building, the obstacle and the distance between the two supports.
  5. 5. The integral corridor hoisting method under the condition of no space utilization is characterized by comprising the following steps: Step a, dividing the corridor into a plurality of sections according to the overall design structure of the corridor; Step b, splicing the two ends to the middle in sequence until the positions of the two ends are at unfavorable space positions, and at least two sections of the corridor to be spliced remain; Step c, lifting the corridor which is close to the unfavorable space position by adopting the corridor lifting method under the unfavorable space condition of any one of claims 1 to 4; and d, hoisting the main body of the corridor of the remaining section in sequence.
  6. 6. The method for lifting the whole corridor under the condition of no space utilization as claimed in claim 5, wherein the two ends of the whole corridor are provided with height differences.
  7. 7. The method for integrally hoisting the corridor under the condition of no space utilization as claimed in claim 5, wherein the method is characterized in that cranes and manual hoists with different specifications are adopted.

Description

Corridor hoisting and integral hoisting method under condition of no interest space Technical Field The invention relates to the technical field of construction of building galleries, in particular to a gallery hoisting and integral hoisting method under the condition of no space. Background In the building construction field of the corridor, the conventional steel structure assembling method comprises the steps of carrying out assembling after carrying out bulk or sheet-shaped transportation on site on the steel structure, and then lifting in place or jacking the steel structure corridor to a corresponding bracket in an integral jacking mode, so that the circulating operation can be carried out until the hoisting process is completed, and the next working procedure can be carried out. Conventional steel structure assembly requires a wider and relatively flat assembly field to ensure that the on-site hoisting equipment is convenient for in-place hoisting. However, the field conditions, logistics and sites are often limited, the construction cannot be performed by adopting the process, and the extremely tight project period is difficult to ensure. Particularly, under the environment that barriers and buildings are arranged around and the construction width is narrow, the assembly and the hoisting of the corridor are the problems to be solved in the field. Disclosure of Invention Due to the defects in the prior art, the invention provides a corridor hoisting and integral hoisting method under the condition of no space utilization, so as to solve the problem of high corridor hoisting difficulty under the condition of no space utilization in the prior art. In order to achieve the above purpose, the present invention provides the following technical solutions: the corridor hoisting method under the condition of no interest space comprises the following steps: Step 1, calculating the size of units assembled by the corridor according to the field space conditions; step 2, a piece of hoisting equipment is arranged at the far end of the corridor installation section in advance; step 3, sectional assembling the main body of the corridor on the adjacent open ground; step 4, lifting and shifting the whole corridor main body to a certain height below the target position from the ground, suspending the corridor main body, and lifting the far end of the corridor main body by using preset lifting equipment; Step 5, installing a lower suspension rod; Step 6, after the installation of the lower suspension rod is completed, the far end of the corridor main body is lifted, and the near end is landed; Step 7, installing a mounting bracket at the proximal end of the corridor main body; step 8, hoisting the proximal end of the corridor main body by using another hoisting device, and hoisting the hoisting devices at the two ends at the same time until the corridor main body reaches the installation position; And 9, adjusting the corridor main body to a specified position and then fixing. In the step 4, one end of each corridor main body is lifted by adopting two lifting devices, and after the corridor main body is integrally shifted to a target position, the lifting device at the far end is replaced. And 4, the suspended height of the corridor main body is larger than the assembly height of the lower suspension rod. And 5, splicing by adopting a manual hoist. After the lower suspension rod is assembled, the lifting height is adjusted to span the site building, the obstacle and the distance between the two brackets. The integral corridor hoisting method under the condition of no interest space comprises the following steps: Step a, dividing the corridor into a plurality of sections according to the overall design structure of the corridor; Step b, splicing the two ends to the middle in sequence until the positions of the two ends are at unfavorable space positions, and at least two sections of the corridor to be spliced remain; step c, adopting the corridor hoisting method under the condition of unfavorable space, hoisting the corridor close to the unfavorable space position; and d, hoisting the main body of the corridor of the remaining section in sequence. The two ends of the whole corridor are provided with height differences. The assembly and the hoisting of the vestibules of different sections are determined according to the surrounding space and the obstacle condition. And the different sections select a hoisting mode, the specification and the arrangement mode of the hoisting device according to the weight and the volume. The hoisting device comprises cranes and manual hoists of different specifications. Compared with the prior art, the invention has the following advantages or beneficial effects: 1. The narrow and small space in scene is fully utilized, the problems of assembling, hoisting, installing lower suspension rods and the like of the corridor are solved, the smooth proceeding of the hoisting of the corridor is ensu