CN-116427557-B - Secondary pre-embedding construction method and mounting structure for structural embedded part
Abstract
The invention discloses a secondary embedded construction method and an installation structure of a structural embedded part, wherein the method comprises the following steps of mattress layer construction; the method comprises the steps of vertically embedding first embedded bars around a region corresponding to a pre-installation position of a structural embedded part in a mattress layer, vertically embedding second embedded bars in the region corresponding to the pre-installation position of the structural embedded part, pouring a concrete mattress layer on the mattress layer, binding the structural bars on the concrete mattress layer, welding and fixing the first embedded bars and the structural bars, installing the structural embedded part in the structural bars, welding and fixing the bars at the lower end of the structural embedded part and the second embedded bars, and pouring structural reinforced concrete. According to the invention, the structural steel bars and the structural embedded parts are respectively welded with different embedded steel bars, so that the embedded steel bars can be independently fixed and bear the load born by the structural embedded parts in the construction process, and on the other hand, the bearing capacity and rigidity of the reinforcement cage in the peripheral area of the structural embedded parts are enhanced, the structural embedded parts are protected from disturbance, and the accuracy of the spatial position of the structural embedded parts is ensured.
Inventors
- LI HONGMIAO
- ZHANG YURONG
- LIU GUOWEI
- HUANG NING
- CAO QINGYING
- LEI QILING
- JIANG MINGMIN
- WANG WANQIONG
Assignees
- 珠海十字门中央商务区建设控股有限公司
Dates
- Publication Date
- 20260508
- Application Date
- 20230423
Claims (3)
- 1. The secondary pre-embedding construction method for the structural embedded part is characterized by comprising the following steps of: performing mattress layer construction according to design requirements; Vertically embedding first embedded bars around a region corresponding to the pre-installation position of the structural embedded part in the mattress layer, and vertically embedding second embedded bars in the region corresponding to the pre-installation position of the structural embedded part, wherein the first embedded bars are higher than the second embedded bars; pouring a concrete cushion layer on the mattress cushion layer, wherein the thickness of an area corresponding to the preinstallation position of the structural embedded part in the concrete cushion layer is larger than that of the peripheral area; Binding structural steel bars on the concrete cushion layer, wherein the first embedded steel bars and the structural steel bars are the same in height and are welded and fixed, and the upper layer and the lower layer of the structural steel bars are welded and fixed with the upper end and the middle end of the first embedded steel bars respectively; The method comprises the steps that a structural embedded part is arranged in structural steel bars, steel bars at the lower end of the structural embedded part are welded and fixed with second embedded steel bars, the second embedded steel bars comprise vertical long steel bars and transverse short steel bars perpendicular to the vertical long steel bars, the transverse short steel bars are welded and fixed on the vertical long steel bars, and the transverse short steel bars are embedded into the concrete cushion layer; And pouring structural reinforced concrete.
- 2. The method for secondary embedding construction of a structural embedded part according to claim 1, further comprising the steps of, before the mattress layer is constructed: Excavating earth to a designed elevation, and checking a groove; and paying off to mark the pre-installation position of the structural embedded part.
- 3. The utility model provides a structure built-in fitting mounting structure which characterized in that includes: a mattress pad layer; The concrete cushion layer is poured on the mattress layer; The lower ends of the first embedded bars and the second embedded bars are embedded and fixed on the mattress layer and the concrete cushion layer, and the first embedded bars are higher than the second embedded bars; The structural steel bars are bound on the concrete cushion layer, and the middle end and the upper end of the first embedded steel bar are welded and fixed with the structural steel bars; the structure embedded part is arranged in the structure steel bars, the steel bars at the lower end of the structure embedded part are welded and fixed with the second embedded steel bars, and the first embedded steel bars are arranged around the structure embedded part.
Description
Secondary pre-embedding construction method and mounting structure for structural embedded part Technical Field The invention relates to the technical field of construction of structural embedded parts, in particular to a secondary embedded construction method and a mounting structure of a structural embedded part. Background The structure embedded part is widely applied to reinforced concrete structures and used for connecting and fixing curtain walls, awning, installation equipment and the like. At present, in the prior art, after the construction of a structural steel bar is completed, a structural embedded part is welded and fixed on the structural steel bar, and then concrete is poured, so that the structural embedded part fixed by the method is extremely easy to be disturbed to deviate from the original position in the process of structural mold sealing or concrete pouring, and the installation accuracy of the embedded part is limited. The method can meet the requirements for common curtain walls, awning and the like with low requirements on the installation accuracy of the structural embedded parts, but the method can directly influence the normal use of the structural embedded parts on the accuracy of the space positions of wagon balance and high-end informationized equipment (such as top-mounted vehicle inspection equipment, large H986 and the like), so that the requirement on the installation accuracy of the structural embedded parts is high, and the conventional technical method is difficult to realize. In order to solve the technical problems, the invention provides a secondary embedded construction method and a secondary embedded construction structure for improving the stability and the installation accuracy of a structural embedded part. Disclosure of Invention The invention aims to provide a secondary embedded construction method and an installation structure of a structural embedded part, the invention respectively welds the structural steel bars and the structural embedded part with different embedded steel bars by arranging two embedded steel bars in a concrete cushion layer, the embedded bars can be independently fixed and bear the load born by the structural embedded part in the construction process, and on the other hand, the bearing capacity and the rigidity of the reinforcement cage in the peripheral area of the structural embedded part are enhanced, the structural embedded part is protected from disturbance, and the accuracy of the spatial position of the structural embedded part is ensured. In order to achieve the above purpose, the invention adopts the following technical scheme: on the one hand, the invention provides a secondary pre-embedding construction method of a structural pre-embedded part, which comprises the following steps: performing mattress layer construction according to design requirements; Vertically embedding first embedded bars around a region corresponding to the pre-installation position of the structural embedded part in the mattress layer, and vertically embedding second embedded bars in the region corresponding to the pre-installation position of the structural embedded part, wherein the first embedded bars are higher than the second embedded bars; pouring a concrete cushion layer on the mattress cushion layer; Binding structural steel bars on the concrete cushion layer, wherein the first embedded steel bars and the structural steel bars are the same in height and are welded and fixed; A structural embedded part is arranged in the structural steel bar, and the steel bar at the lower end of the structural embedded part is welded and fixed with the second embedded steel bar; And pouring structural reinforced concrete. Further, before the mattress layer is constructed, the method further comprises the following steps: Excavating earth to a designed elevation, and checking a groove; and paying off to mark the pre-installation position of the structural embedded part. Further, the thickness of the area of the concrete cushion layer corresponding to the pre-installation position of the structural embedded part is larger than that of the peripheral area. Further, the second embedded steel bar comprises a vertical long steel bar and a transverse short steel bar perpendicular to the vertical long steel bar, the transverse short steel bar is welded and fixed on the vertical long steel bar, and the transverse short steel bar is embedded into the concrete cushion layer. Further, the upper layer and the lower layer of the structural steel bars are welded and fixed with the upper end and the middle end of the first embedded steel bars respectively. In another aspect, the present invention provides a structural embedment mounting structure, comprising: a mattress pad layer; The concrete cushion layer is poured on the mattress layer; The lower ends of the first embedded bars and the second embedded bars are embedded and fixed on the mattress layer and the concrete cushion