Search

CN-116677059-B - Permanent-face combination structure and method for building water delivery

CN116677059BCN 116677059 BCN116677059 BCN 116677059BCN-116677059-B

Abstract

The invention discloses a permanent face combining structure for building water delivery, which comprises a plurality of water collecting grooves, a water draining groove and a water draining groove, wherein the water collecting grooves are all arranged at low-lying positions of the ground surface, a plurality of first cover plates are detachably arranged at the top opening positions of the water collecting grooves to cover the water collecting grooves, a plurality of first water filtering holes are formed in the first cover plates, a plurality of second cover plates are detachably arranged at the top opening positions of the water draining grooves to cover the water collecting grooves, a plurality of second water filtering holes are formed in the second cover plates, a plurality of filtering grooves which are arranged and spliced along the extending direction of the water draining grooves are detachably arranged in the water draining grooves and are divided into a filtering part and a water draining part which are arranged up and down, the filtering part is communicated with the lowest end of each water collecting groove, and the water draining part is communicated with a water collecting tank. According to the invention, the first cover plate with the first water filtering holes is detachably arranged at the open top of the water collecting groove to filter rainwater and sewage, so that large-particle sand is intercepted outside the water collecting groove, and the occurrence of blockage of the water collecting groove by sand is effectively avoided.

Inventors

  • LI JIANYONG
  • SANG HAO
  • DONG YE
  • LU XIANYANG
  • Me Xuechun
  • TANG YONG
  • Ji Guokui
  • Zhang Zikuo
  • ZHENG ZEHAO
  • ZHOU BOHAN
  • LI JIAXIANG

Assignees

  • 中交建筑集团东南建设有限公司
  • 中交建筑集团有限公司

Dates

Publication Date
20260512
Application Date
20230620

Claims (9)

  1. 1. Building water delivery is with facing combination structure forever, its characterized in that includes: The water collection grooves are all arranged at the low-lying position of the ground surface, a plurality of first cover plates are detachably arranged at the top opening positions of the water collection grooves to cover the water collection grooves, and a plurality of first water filtering holes are formed in the first cover plates; The drainage groove is detachably provided with a plurality of second cover plates for covering the drainage groove, the second cover plates are provided with a plurality of second water filtering holes, a plurality of filter tanks which are arranged and spliced along the extending direction of the drainage groove are detachably arranged in the drainage groove and are divided into a filter part and a drainage part which are arranged up and down, the filter part is communicated with the lowest end of each water collecting groove, and the drainage part is communicated with a water collecting tank; The second cover plate includes: The support frame is arranged at the top of the water collecting groove, and a chute perpendicular to the extending direction of the water collecting groove is arranged on the support frame; the filter plate is arranged on the supporting frame and is provided with the second water filtering holes; The movable plate is arranged on the supporting frame in a sliding manner and covers the top of the water collecting groove together with the filter plate, a sliding block is arranged at the bottom of the movable plate, the sliding block is arranged in the sliding groove in a moving manner, and when the sliding block slides to the filter plate, the movable plate is located right above the filter plate and tangent to the upper surface of the filter plate.
  2. 2. The permanent temporary connection structure for building water delivery according to claim 1, further comprising a plurality of water delivery pipes, wherein the top of each water delivery pipe is communicated with a rainwater outlet at the top of the house, and the bottom of each water delivery pipe is communicated with a corresponding water collecting groove.
  3. 3. The permanent face combining structure for water delivery of building according to claim 2, wherein the top of the water delivery pipe is funnel-shaped, a top cover is hinged above the water delivery pipe on the wall of the building, the top cover is obliquely arranged far away from the building and covers the top opening of the water delivery pipe, and a third water filtering hole is arranged on the top cover.
  4. 4. The permanent-face combination structure for water delivery of building according to claim 2, wherein a rotating shaft coaxial with the water delivery pipe is rotatably arranged in the water delivery pipe through a bracket, a plurality of rotating blades which are spirally arranged are arranged on the periphery of the rotating shaft, a scraping plate parallel to the rotating shaft is further arranged on the rotating shaft, and bristles are arranged on the edge, close to the inner wall of the water delivery pipe, of the scraping plate.
  5. 5. The permanent-facing combination structure for building water delivery according to claim 2, wherein a filter box is arranged between the water collecting groove and the water delivery pipe, a limit cylinder is arranged at the top of the filter box, a water inlet hole is formed in the top wall of the filter box in the limit cylinder, the bottom of the water delivery pipe is inserted into the limit cylinder, a drawing hole is formed in the side wall of the filter box, a filter drawer is inserted into the drawing hole, a water outlet hole is formed in the bottom of the filter drawer, a filter layer is arranged in the filter drawer, and a water outlet hole is formed in the bottom wall of the filter box.
  6. 6. The permanent-face combination structure for building water delivery according to claim 1, wherein a water collecting tank is arranged at the bottom of the water collecting groove, a plurality of groups of support plates spliced up and down are arranged on the side wall of the water collecting groove, a plurality of first connecting slots are arranged at the top of the water collecting tank, a second connecting slot is arranged at the top of the support plate, a first connecting plug is arranged at the bottom of the support plate, a second connecting plug is arranged at the bottom of the first cover plate, the second connecting plug is inserted in a corresponding second connecting slot in the uppermost support plate, the first connecting plug of the uppermost support plate is inserted in a corresponding second connecting slot in the lower support plate, and the first connecting plug of the lowermost support plate is inserted in a corresponding first connecting slot.
  7. 7. The permanent connection structure for building water delivery according to claim 1, wherein the filter tanks are U-shaped, two adjacent filter tanks are connected by a U-shaped connecting piece, connecting grooves are formed at two ends of the connecting piece, and two adjacent filter tanks are respectively inserted into two connecting grooves of the same connecting piece.
  8. 8. The permanent face combining structure for building water delivery according to claim 7, wherein clamping blocks are arranged on two sides of the top of the filter tank, limiting blocks are arranged on the side walls of the drainage grooves, a plurality of limiting grooves are arranged on the limiting blocks, and the clamping blocks are clamped in the corresponding limiting grooves.
  9. 9. The construction method of the permanent combined structure for building water transportation according to any one of claims 1 to 8, comprising the steps of: firstly, prefabricating a first cover plate, a second cover plate and a filter tank, and simultaneously digging a water collecting groove, a water draining groove and a water collecting pool; Step two, splicing and installing a filter tank in the drainage groove, and simultaneously arranging a first cover plate on the water collecting groove; and thirdly, arranging a second cover plate on the drainage groove.

Description

Permanent-face combination structure and method for building water delivery Technical Field The invention relates to the technical field of building construction, in particular to a permanent face combination structure and method for building water delivery. Background Perpetual forest bonding means that in the construction process of a building, a part of the building needs to be built, but the function of the part needs to be used in temporary engineering, so that the construction cost is increased to avoid repeated building, and the part is usually finished in advance. Water delivery and drainage channels and the like are common permanent forest combining structures. In the building construction process, the comprehensive drainage and utilization of precipitation and accumulated water on a construction site are required, the cleanliness of the construction site is ensured, and the recycling force of water resources is increased, so that the purposes of water conservation, energy conservation and environmental protection are achieved. At present, when a construction site is constructed, a drainage groove is generally adopted to bear the tasks of water delivery and drainage of rainwater, sewage and the like on the site, when accumulated water on the site is required to be transferred, a worker can directly start a water suction pump to directly pump the accumulated water into the drainage groove and drain the accumulated water along the drainage groove, but the accumulated water on the existing site is often mixed with some sediment or broken stone, the sediment or broken stone can be conveyed into the drainage groove along with the accumulated water, and the water suction pump can be damaged and the drainage groove can be blocked for a long time, so that normal water delivery and drainage are affected. Disclosure of Invention The invention provides a permanent temporary combination structure for building water delivery, which enables rainwater and sewage to automatically flow to a water collecting groove by arranging the water collecting groove at a low-lying position on the ground surface, omits the use of a water suction pump, and can be detachably provided with a first cover plate with a first water filtering hole at the top opening of the water collecting groove to filter the rainwater and the sewage so as to cut off large-particle sand and stone outside the water collecting groove, thereby effectively avoiding the sand and stone from blocking the water collecting groove. To achieve these objects and other advantages and in accordance with the purpose of the invention, there is provided a permanent magnet coupling structure for water transportation of a building, comprising: The water collection grooves are all arranged at the low-lying position of the ground surface, a plurality of first cover plates are detachably arranged at the top opening positions of the water collection grooves to cover the water collection grooves, and a plurality of first water filtering holes are formed in the first cover plates; The drainage ditch groove, its open department in top can be dismantled and be provided with a plurality of second apron and cover it, be provided with a plurality of second drainage holes on the second apron, can dismantle in the drainage ditch groove and be provided with a plurality of filter tanks of arranging the concatenation along its extending direction and divide into filter unit and the drainage portion that set up from top to bottom with it, filter unit communicates with the extreme bottom of each water collecting ditch groove, drainage portion communicates with the catch basin. Preferably, the permanent temporary combination structure for building water delivery further comprises a plurality of water delivery pipes, wherein the top of each water delivery pipe is communicated with a rainwater outlet at the top of a house, and the bottom of each water delivery pipe is communicated with a corresponding water collecting groove. Preferably, in the permanently adjacent combination structure for building water delivery, the top of the water delivery pipe is in a funnel shape, a top cover is hinged above the water delivery pipe on the wall of the house, the top cover is obliquely arranged far away from the house direction and covers the top opening of the water delivery pipe, and a third water filtering hole is formed in the top cover. Preferably, in the permanent-face combination structure for building water delivery, a rotating shaft coaxial with the water delivery pipe is rotatably arranged in the water delivery pipe through a bracket, a plurality of rotating blades which are spirally arranged are arranged on the periphery of the rotating shaft, a scraping plate parallel to the rotating shaft is further arranged on the rotating shaft, and bristles are arranged on the edge, close to the inner wall of the water delivery pipe, of the scraping plate. Preferably, in the building water delivery is w