CN-117151631-B - Construction progress monitoring and management system based on wisdom building site
Abstract
The invention belongs to the technical field of construction supervision, and particularly relates to a construction progress monitoring and management system based on an intelligent construction site, which comprises a server, a project progress detection and analysis module, a project construction preliminary diagnosis module, a construction ring diagnosis and evaluation module and a project supervision diagnosis module; according to the invention, the construction progress of all construction projects on a construction site is accurately analyzed and fed back, step-by-step reason judgment is carried out when the construction progress unqualified condition occurs on the corresponding construction date of the corresponding construction project, a manager can accurately and timely master the progress abnormal reason and correspondingly adjust subsequent management measures, the construction projects corresponding to the construction progress unqualified signals are analyzed to determine difficult-to-finish projects, the construction projects corresponding to the construction progress qualified signals are analyzed to determine preferable lottery projects, and the distance matching analysis is carried out on all preferable lottery projects and the corresponding difficult-to-finish projects, so that the reasonable allocation of personnel of each construction project is realized.
Inventors
- LU HUIFENG
- LIU HAINING
- ZHU LIMING
- WANG XIANGHONG
- WANG JING
- HUANG YANGCHENG
- Hui Xinwen
- LIU XIAOLONG
Assignees
- 苏州中恒通路桥股份有限公司
Dates
- Publication Date
- 20260508
- Application Date
- 20230817
Claims (7)
- 1. The intelligent construction site-based construction progress monitoring management system is characterized by comprising a server, a project progress detection analysis module, a project construction preliminary diagnosis module, a construction ring diagnosis evaluation module and a project supervision diagnosis module, wherein the server acquires all construction projects of a corresponding construction site, marks the corresponding construction projects as i, i is a positive integer larger than 1, acquires preset construction days of a preset construction project i, sets a daily preset construction progress value of the construction project i based on the preset construction days and generates a construction progress policy curve of the construction project i according to the preset construction progress value, and sends the construction progress policy curve to the server for storage; The construction progress disqualification signal of the construction project i is sent to a project construction preliminary diagnosis module through a server, the project construction preliminary diagnosis module carries out preliminary diagnosis of abnormal reasons on the construction project i after receiving the construction progress disqualification signal so as to judge the relevance between the current date construction progress disqualification and the earlier construction delay, and preliminary judgment information is sent to the server when the current date construction progress disqualification caused by the earlier construction delay is judged, otherwise, a construction environment diagnosis signal is generated and sent to a construction environment diagnosis evaluation module through the server; The Shi Huan diagnosis and evaluation module performs diagnosis and analysis on the construction environment condition of the current date of the construction project i after receiving the construction environment diagnosis signal, so as to judge the relevance between the construction progress disqualification of the current date and the construction environment condition, generate a construction environment normal signal or a construction environment abnormal signal, send the construction environment abnormal signal to a construction supervision early warning end through a server, and send the construction environment normal signal to the project supervision and diagnosis module; the specific operation process of the project construction preliminary diagnosis module comprises the following steps: the method comprises the steps of obtaining construction progress detection information of a construction project i on the adjacent last date, generating a construction environment diagnosis signal and sending the construction environment diagnosis signal to a construction ring diagnosis evaluation module through a server if the adjacent last date progress is qualified, subtracting the actual construction progress value of the current date from the actual construction progress value of the adjacent last construction date to obtain an actual increment value if the adjacent last date progress is unqualified, carrying out vertical distance calculation on the current date of a construction progress strategy curve and a progress preset point of the adjacent last date to obtain a preset increment value, generating the construction environment diagnosis signal and sending the construction environment diagnosis signal to the construction ring diagnosis evaluation module through the server if the actual increment value does not exceed the preset increment value, judging that the construction progress of the current date is unqualified due to earlier construction delay, and sending preliminary judgment information to the server.
- 2. The intelligent worksite-based construction progress monitoring and management system according to claim 1, wherein the specific operation process of the project progress detection and analysis module comprises: The method comprises the steps of collecting an actual construction progress value of a current date of a construction project i, placing the actual construction progress value into a construction progress strategy curve to form a progress actual measurement point, marking a coordinate point corresponding to the current date on the construction progress strategy curve as a progress preset point, generating a progress qualification signal if the progress actual measurement point is located above or coincides with the progress preset point, connecting the progress preset point and the progress actual measurement point through a line segment if the progress actual measurement point is located below the progress preset point, marking the line segment as a progress deviation line segment, calculating the length of the progress deviation line segment and marking the progress deviation line segment as a progress deviation value, and generating a progress disqualification signal if the progress deviation value exceeds a preset progress deviation threshold value, otherwise, generating the progress qualification signal.
- 3. The intelligent worksite-based construction progress monitoring and management system according to claim 1, wherein the specific analysis process of the construction progress diagnosis and evaluation module comprises: Setting a plurality of detection time periods in the construction time period of the current date, marking the area of the corresponding construction project i as an analysis area, marking the corresponding detection time period as u, and marking u as a natural number larger than 6; the temperature data, the humidity data, the ultraviolet data, the rainfall data and the air pollution data of the analysis area detection period u are obtained through analysis, and the temperature data, the humidity data, the ultraviolet data, the rainfall data and the air pollution data are normalized to obtain Shi Huan coefficients of the detection period u; Calculating the ratio of the number of construction negative influence time periods and the number of construction positive influence time periods of the current date to obtain a ring-setting primary evaluation coefficient, if Shi Huan primary evaluation coefficient exceeds a pre-facility ring primary evaluation coefficient threshold, judging that the construction progress of the current date is unqualified due to poor construction environment; And carrying out numerical calculation on the ring construction initial evaluation coefficient and Shi Huan expression values to obtain a ring construction final evaluation coefficient, if the Shi Huan final evaluation coefficient exceeds a preset ring construction final evaluation coefficient threshold value, judging that the construction progress is unqualified on the current date due to poor construction environment, generating a construction environment abnormal signal, otherwise, generating a construction environment normal signal, and transmitting the construction environment normal signal to a project supervision and diagnosis module through a server.
- 4. The construction progress monitoring and management system based on the intelligent construction site according to claim 3, wherein the analysis and acquisition method of temperature data, humidity data, ultraviolet data, rainfall data and air pollution data is as follows: Acquiring a real-time temperature curve of an analysis area detection period u, establishing a temperature rectangular coordinate system taking time as an X axis and temperature as a Y axis, making a temperature upper limit straight line and a temperature lower limit straight line which are parallel to the X axis in the temperature rectangular coordinate system, placing the real-time temperature curve into the temperature rectangular coordinate system, marking the time length of the real-time temperature curve in the two temperature straight lines as proper temperature time length, marking an area surrounded by the real-time temperature curve and the upper limit straight line and an area surrounded by the real-time temperature curve and the lower limit straight line as a temperature deviation area, acquiring the area of the temperature deviation area and marking the area as a temperature deviation coefficient, and carrying out numerical calculation on the temperature deviation coefficient and proper temperature time length to acquire temperature data; the ultraviolet intensity curve, the rainfall curve and the air pollution degree curve of the analysis area detection period u are acquired, a plurality of analysis sites are randomly acquired on the ultraviolet intensity curve, the ultraviolet intensity values corresponding to all the analysis sites are summed up and calculated, the average value is obtained to obtain ultraviolet data, and rainfall data and air pollution data are acquired in a similar way.
- 5. A construction progress monitoring and management system based on an intelligent construction site according to claim 3, wherein the specific operation process of the project supervision and diagnosis module comprises: Acquiring an actual constructor reduction value of a current date construction project i and effective construction time of each constructor, marking constructors which do not exceed a preset effective construction time threshold as abnormal constructors, and calculating the ratio of the number of the abnormal constructors to the current actual constructors to obtain an abnormal constructor occupation ratio; If the actual constructor number drop value does not exceed the preset actual constructor number drop threshold value and the abnormal constructor ratio does not exceed the preset abnormal constructor ratio threshold value, summing up and calculating the effective construction time lengths of all constructors and taking an average value to obtain an average construction time length, if the average construction time length does not exceed the preset average construction time length threshold value, judging that the construction progress on the current date is unqualified and a construction supervision unqualified signal is generated due to poor construction supervision, and if the average construction time length exceeds the preset average construction time length threshold value, generating a construction training signal.
- 6. The construction progress monitoring and managing system based on the intelligent construction site according to claim 1, wherein the server is in communication connection with the project completion emergency evaluation module, the server sends a construction progress disqualification signal to the project completion emergency evaluation module, when the project completion emergency evaluation module receives the construction progress disqualification signal, the actual start construction date of the construction project i is acquired, the time difference between the current date and the actual start construction date is calculated to obtain the actual construction days, the construction days preset by the construction project i are subtracted by the actual construction days to obtain a construction period difference value, and the construction period difference value is calculated by the ratio of the preset construction days to obtain a construction period representation value; The method comprises the steps of acquiring an actual construction progress value of a current date of a construction project i, obtaining a to-be-completed progress value of the construction project i according to the actual construction progress value, carrying out numerical calculation on the construction deadline representation value and the to-be-completed progress value to obtain a project representation coefficient, marking a corresponding construction project i as a difficult-to-complete project if the project representation coefficient exceeds a preset project representation coefficient threshold value, and sending the difficult-to-complete project to a construction supervision and early warning end through a server so as to timely carry out personnel supplement of the corresponding difficult-to-complete project.
- 7. The intelligent construction site-based construction progress monitoring and managing system according to claim 6, wherein when personnel replenishment of a project which is difficult to complete is required, the construction project which corresponds to a qualified signal of the construction progress is marked as a project to be pumped, a progress value and a construction period limit representation value which correspond to the project to be pumped are obtained, the project to be pumped, of which the progress value to be completed does not exceed a preset progress threshold and the construction period limit representation value exceeds a preset construction period representation threshold, is marked as a preferable pumping project; And acquiring the regional positions of the corresponding difficult-to-finish items and the regional positions of all the preferred drawing items, so as to obtain the path distance values of the corresponding difficult-to-finish items and the corresponding preferred drawing items, marking the preferred drawing item with the minimum path distance value as the preferred drawing item of the corresponding difficult-to-finish item, and sending the preferred drawing item of the corresponding difficult-to-finish item to a construction supervision and early warning end through a server.
Description
Construction progress monitoring and management system based on wisdom building site Technical Field The invention relates to the technical field of construction supervision, in particular to a construction progress monitoring and management system based on an intelligent construction site. Background The construction site generally refers to a site for carrying out works such as engineering construction or production, manufacturing and the like, is a very important concept in the fields of construction industry, manufacturing industry and the like, is not only an important place for production and construction, but also a key link for realizing engineering targets and completing customer demands, so that in the engineering implementation process, the construction site needs to be scientifically managed and effectively monitored to ensure engineering quality and safety; When construction is carried out on a building site, a plurality of construction projects are required to be carried out on the corresponding site at the same time, so that the accurate analysis and feedback of the construction progress of all the construction projects on the site are difficult at present, step-by-step reason judgment cannot be carried out when the construction progress is unqualified on the corresponding construction date of the corresponding construction project, a manager cannot accurately and timely master the abnormal reason of the progress and correspondingly carry out subsequent management measure adjustment, and personnel among the construction projects cannot be reasonably allocated in time, so that construction management is not facilitated; in view of the above technical drawbacks, a solution is now proposed. Disclosure of Invention The invention aims to provide a construction progress monitoring and managing system based on an intelligent construction site, which solves the problems that in the prior art, the construction progress of all construction projects on the construction site is difficult to accurately analyze and feed back, the construction progress cannot be judged in a step-by-step manner when the construction progress corresponding to the construction date of the corresponding construction project is unqualified, and personnel among the construction projects cannot be reasonably allocated in time, so that the construction management is not facilitated. In order to achieve the above purpose, the present invention provides the following technical solutions: The intelligent construction site-based construction progress monitoring management system comprises a server, a project progress detection analysis module, a project construction preliminary diagnosis module, a construction ring diagnosis evaluation module and a project supervision diagnosis module, wherein the server acquires all construction projects of a corresponding construction site, marks the corresponding construction project as i which is a positive integer greater than 1, acquires preset construction days of a preset construction project i, sets a daily preset construction progress value of the construction project i based on the preset construction days and generates a construction progress strategy curve of the construction project i according to the preset construction progress value, and sends the construction progress strategy curve to the server for storage; The construction progress disqualification signal of the construction project i is sent to a project construction preliminary diagnosis module through a server, the project construction preliminary diagnosis module carries out preliminary diagnosis of abnormal reasons on the construction project i after receiving the construction progress disqualification signal so as to judge the relevance between the current date construction progress disqualification and the earlier construction delay, and preliminary judgment information is sent to the server when the current date construction progress disqualification caused by the earlier construction delay is judged, otherwise, a construction environment diagnosis signal is generated and sent to a construction environment diagnosis evaluation module through the server; The Shi Huan diagnosis and evaluation module is used for carrying out diagnosis and analysis on the construction environment condition of the current date of the construction project i after receiving the construction environment diagnosis signal, judging the relevance between the construction progress disqualification of the current date and the construction environment condition according to the diagnosis and evaluation result, generating a construction environment normal signal or a construction environment abnormal signal, sending the construction environment abnormal signal to a construction supervision early warning end through a server, and sending the construction environment normal signal to the project supervision diagnosis module through the server. Further, the s