Abstract

The invention provides a construction enclosure and a channel protection way arrangement method based on road reconstruction engineering, comprises the construction of a lower part structure of a newly built bridge, the construction of an upper part cast-in-situ beam of the newly built bridge and (3) floor reconstruction, road changing construction and the like. The method has the characteristics of simplicity and clarity, fitting construction site, strong universality, good applicability and the like, and is worthy of popularization.

Inventors

  • GAO YUNJIE
  • LUO HUIJIAN
  • TANG CHAO
  • QU YANG
  • SHI XUYANG
  • FU KUN
  • SHEN XINGDONG

Assignees

  • 中建八局第三建设有限公司

Dates

Publication Date
20260505
Application Date
20231026

Claims (3)

  1. 1. The construction enclosure and the channel protection way arrangement method based on the road reconstruction project are characterized by comprising the following steps: S1, constructing a lower structure of a new bridge, wherein the lower structure of the new bridge comprises a new bridge pile foundation, a new bridge bearing platform and a new bridge pier, the new bridge pier is arranged at the upper end of the new bridge bearing platform, the new bridge bearing platform is arranged at the upper end of the new bridge pile foundation, and when a construction enclosure is arranged, a foundation pit excavation side line of the new bridge bearing platform is used as a construction enclosure arrangement control line; Judging the setting position of the protection passage way on the cross section according to the relative position of the newly built bridge bearing platform and the existing ground road, wherein the setting position of the protection passage way on the cross section is divided into two cases, namely, the center line of the newly built bridge bearing platform is basically consistent with the center line of the existing ground road, after a construction space of a lower structure of the newly built bridge is reserved, when the distance from the side line of the existing ground road is still provided, the middle part of the road cross section is closed by adopting a construction fence, the two sides of the protection passage way are respectively provided with the existing ground road or the newly built temporary road as a social vehicle protection passage way, and the two side protection passage ways are respectively arranged according to a single-lane motor vehicle lane and a single-lane non-motor vehicle lane; S2, constructing a cast-in-situ beam at the upper part of the newly-built bridge, namely erecting a support frame and a scaffold, and constructing the cast-in-situ beam at the upper part of the newly-built bridge, wherein the widths of the support frame and the scaffold after being erected are larger than the widths of the top surfaces of the cast-in-situ beams at the upper part of the newly-built bridge; S3, dividing the ground road into two parts, namely a left part and a right part according to two opposite directions of vehicle running, and carrying out the construction of changing the road, wherein the construction of changing the road is that after the construction of the right part is completed, a construction enclosure of the right part is changed to the left part, the construction of the left part is carried out after the left part is closed, a channel protection way is arranged on the right part of the road which is completed, and if the left part is firstly constructed, the construction is carried out, and the construction is carried out after the left part is completed, the construction is also carried out after the left part is converted to the right part.
  2. 2. The construction fence and the reserved passage way arrangement method based on the road reconstruction project are characterized in that in S2, after construction of a lower structure of a newly built bridge is completed, construction fence shifting is carried out, construction fence shifting is divided into two cases corresponding to S1, firstly, the construction fence in S1 is expanded outwards along the width direction of a road, the widths of a support frame and a scaffold of a cast-in-place beam on the upper portion of the newly built bridge are reserved, the original reserved passage way is occupied after the construction fence is expanded outwards, a vehicle lane cannot pass at the moment, only a reserved passage way which is not passed by the vehicle lane is reserved, secondly, the construction fence on one side of the reserved passage way is expanded outwards, the widths of the support frame and the scaffold of the cast-in-place beam on the upper portion of the newly built bridge are reserved, a part of the reserved passage way on the side of the cast-in-place beam can be reserved after the construction fence on the side is expanded outwards, at the moment, the reserved non-vehicle lane of the vehicle lane is reserved on the side of the reserved passage way is not moved enough in the newly built bridge on the upper portion of the bridge, and the space of the bridge is reserved on the side of the upper portion of the bridge.
  3. 3. The construction fence and the passageway protection way arrangement method based on the road reconstruction project as claimed in claim 2, characterized in that in S3, after the construction of the cast-in-place beam at the upper part of the newly-built bridge is completed, the support frame and the scaffold used by the cast-in-place beam at the upper part of the newly-built bridge are all removed, usable space is reserved under the bridge again, S3 and S2 are correspondingly divided into two cases, firstly, one side construction fence in S2 is expanded to the position of a ground red line along the width direction of the road, the opposite other side construction fence is retracted to the position of a side line of the newly-built bridge pier column along the width direction of the road, thus forming a fence inner working face capable of carrying out construction of a semi-wide ground road, the outside of the retracted construction fence is reserved with a passageway protection way of a social vehicle again, the passageway protection way is set according to a two-way motor vehicle lane and a two-way motor vehicle, after the semi-wide ground road of the first construction is completed, the construction fence is changed to the other semi-wide ground, the construction fence is further completed, the two-way vehicle is changed to the two-way motor vehicle lane and the two-way vehicle is not required to be in the form of the two-way vehicle lane is not being continued, the two-way vehicle is not being retracted to the two-way vehicle lane, the two-way vehicle is not being continued to be closed, the two-way vehicle is not being closed, the two-way vehicle is continued to the two-way vehicle road is not required to be a two-way vehicle road, and the two-way vehicle road is not required to be a road way vehicle road, and a road bridge is left, and a road bridge is not, the constructed half-width ground road is opened as a social vehicle channel-protecting road and is arranged in a form of a two-way traffic double-lane motor vehicle lane and a two-way non-motor vehicle lane.

Description

Construction enclosure and channel protection way arrangement method based on road reconstruction engineering Technical Field The invention relates to the technical field of construction of road reconstruction projects, in particular to a construction enclosure and a channel protection way arrangement method based on the road reconstruction projects. Background With the further improvement of the urban degree of China, the original roads in more and more cities can not meet the increasing demand of traffic, and the road reconstruction and expansion projects are increased, especially the form of old road expansion and new bridge becomes the first choice of a plurality of cities. However, the road reconstruction and expansion in the city is often difficult to completely interrupt traffic and close the construction site, and a reserved channel protection way for the coming and going of the social vehicles is needed, so that how to scientifically and reasonably arrange the site construction enclosure and the channel protection way, and further ensure that the engineering progress is not influenced and the requirements of the social vehicles on passing can be met to the greatest extent are the urgent problem of engineering technicians. Disclosure of Invention Aiming at the prior art, the invention provides a construction enclosure and a channel protection way arrangement method based on a road reconstruction project. The invention provides a construction enclosure and a channel protection way arrangement method based on a road reconstruction project, which comprises the following steps: S1, constructing a lower structure of a new bridge, wherein the lower structure of the new bridge comprises a new bridge pile foundation, a new bridge bearing platform and a new bridge pier, the new bridge pier is arranged at the upper end of the new bridge bearing platform, the new bridge bearing platform is arranged at the upper end of the new bridge pile foundation, and when a construction enclosure is arranged, a foundation pit excavation side line of the new bridge bearing platform is used as a construction enclosure arrangement control line; S2, constructing a cast-in-situ beam at the upper part of the newly-built bridge, namely erecting a support frame and a scaffold, and constructing the cast-in-situ beam at the upper part of the newly-built bridge, wherein the widths of the support frame and the scaffold after being erected are larger than the widths of the top surfaces of the cast-in-situ beams at the upper part of the newly-built bridge; S3, dividing the ground road into two parts, namely a left part and a right part according to two opposite directions of vehicle running, and carrying out the construction of changing the road, wherein the construction of changing the road is that after the construction of the right part is completed, a construction enclosure of the right part is changed to the left part, the construction of the left part is carried out after the left part is closed, a channel protection way is arranged on the right part of the road which is completed, and if the left part is firstly constructed, the construction is carried out, and the construction is carried out after the left part is completed, the construction is also carried out after the left part is converted to the right part. In the S1, the setting position of the protection passage way on the cross section is judged according to the relative position of the newly built bridge bearing platform and the existing ground road, and the two situations are classified as one of the newly built bridge bearing platform center line and the existing ground road center line, wherein after a construction space of the lower structure of the newly built bridge is reserved, when the distance from the existing ground road side line is still provided, the middle part of the road cross section is closed by adopting a construction fence, the two sides of the protection passage way are respectively set according to a single-lane motor vehicle lane and a single-lane non-motor vehicle lane by utilizing the existing ground road or the newly built temporary road, and the two sides of the protection passage way are respectively set according to the single-lane motor vehicle lane and the single-lane non-motor vehicle lane. In the S2, after the construction of the lower structure of the newly built bridge is completed, the construction fence is moved, and the construction fence is moved and the corresponding construction fence in the S1 is divided into two cases, namely, the construction fence in the S1 is expanded outwards along the width direction of the road, the widths of the support frame and the scaffold of the cast-in-situ beam at the upper part of the newly built bridge are reserved, the original reserved passage way is occupied after the construction fence is expanded outwards, the motor vehicle lane can not pass through at the moment, only the reserved passage w