Abstract

The invention relates to the technical field of construction equipment and discloses wind measuring tower installation construction equipment which comprises a tower body, a balance arm, a linear movement module and a movable winch, wherein the balance arm is arranged on the upper end face of the tower body, the linear movement module is arranged at the bottom of the balance arm, the movable winch is arranged outside the output end of the linear movement module, the balance arm and the outside of the tower body are respectively connected with a first winch and a second winch, and a control mechanism is arranged at the bottom of the movable winch. This wind measuring tower installation construction equipment, the sliding fit of track groove and protective housing, guide arm on the roof can provide direction and spacing for the rotary motion of fixed assembly seat, ensures the stability in its operation in-process, effectively avoids the assembly jig to appear not hard up or the condition of shifting, wholly promotes operation convenience and the job stabilization nature in the wind measuring tower installation construction process, ensures the overall quality of wind measuring tower assembly jig installation construction.

Inventors

  • ZHANG SHENGFA

Assignees

  • 海南州华豫新能源开发有限公司

Dates

Publication Date
20260505
Application Date
20260206

Claims (10)

  1. 1. The wind measuring tower installation construction equipment comprises a tower body (1), a balance arm (13), a linear movement module (15) and a movable winch (3), wherein the balance arm (13) is arranged on the upper end face of the tower body (1), the linear movement module (15) is arranged at the bottom of the balance arm (13), and the movable winch (3) is arranged outside the output end of the linear movement module (15), and is characterized in that the balance arm (13) and the outer part of the tower body (1) are respectively connected with a first winch (2) and a second winch (21), the bottom of the movable winch (3) is provided with a control mechanism (4), two sides of the outer part of the control mechanism (4) are respectively connected with control steel cables (22), and the two groups of control steel cables (22) are respectively connected with the output ends of the first winch (2) and the second winch (21). Control mechanism (4) are including roof (41), the inner chamber top of roof (41) is provided with gear motor (44), the output of gear motor (44) is connected with fixed assembly seat (43), the top of fixed assembly seat (43) is provided with protective housing (42) and guide arm (45) respectively, the track groove with protective housing (42) and guide arm (45) looks adaptation has been seted up to the bottom of roof (41), track groove and protective housing (42) and guide arm (45) sliding connection, the bottom of fixed assembly seat (43) is connected with fixture (5), fixture (5) include universal ball (51), the output of universal ball (51) is connected with grip block (52), evenly be provided with hydro-cylinder (53) between grip block (52) and the fixed assembly seat (43) to the bottom of grip block (52) is connected with centre gripping module (54).
  2. 2. The wind measuring tower installation construction device according to claim 1, wherein a reinforcing block (46) is arranged at the top of the top plate (41), and the outside of the reinforcing block (46) is connected with the output end of the movable hoist (3) through bolts.
  3. 3. The wind measuring tower installation construction device according to claim 1, wherein the outer sides of the top plate (41) are provided with assembly rings, and the outer parts of the assembly rings are connected with two groups of control steel cables (22).
  4. 4. The wind measuring tower installation construction device according to claim 1, wherein the tower body (1) comprises a base, reinforcing arms (11) are uniformly arranged outside the base, and the tops of the reinforcing arms (11) are connected with balance arms (13).
  5. 5. The wind measuring tower installation construction device according to claim 1, wherein a cab (14) is arranged outside the balance arm (13), a protective shell is arranged outside the cab (14), and a control module is arranged in an inner cavity of the cab (14).
  6. 6. The wind measuring tower installation construction device according to claim 2, wherein a jacking mechanism (12) is arranged outside the reinforcing arm (11), and the other end of the jacking mechanism (12) is connected with the outside of the cab (14) through bolts.
  7. 7. A wind measuring tower installation construction device according to claim 5, wherein the top of the tower body (1) is provided with a reinforcing steel cable (16), the outside of the reinforcing steel cable (16) is provided with a reinforcing rib, and the other end of the reinforcing steel cable (16) is connected with the right side of the cab (14).
  8. 8. The wind measuring tower installation construction device according to claim 1, wherein an anti-slip gasket is arranged outside the clamping module (54), the anti-slip gasket is in fit connection with a clamping surface of the clamping module (54), a rolling wheel is arranged at the end part of the guide arm (45), and the rolling wheel is in rolling fit with a track groove at the bottom of the top plate (41).
  9. 9. The wind measuring tower installation construction device according to claim 4, wherein a protective sleeve is arranged outside the reinforcing arm (11), and the protective sleeve is wrapped at the connection part of the reinforcing arm (11) and the base of the tower body (1).
  10. 10. The wind measuring tower installation construction device according to claim 7, wherein a dust cover is arranged outside the control module, the dust cover is detachably connected with the inner cavity wall of the cab (14) through a buckle, a buffer joint is arranged at the connection part of the reinforced steel cable (16) and the cab (14), and the buffer joint is fixedly connected with the end part of the reinforced steel cable (16).

Description

Wind measuring tower installation construction equipment Technical Field The invention relates to the technical field of construction equipment, in particular to wind measuring tower installation construction equipment. Background The wind measuring tower installation construction equipment belongs to the field of core construction equipment in wind measuring tower construction engineering, is mainly applied to key construction links such as lifting, azimuth adjustment, angle adjustment and contraposition installation of a wind measuring tower assembly frame, covers the integrated application of relevant technologies such as lifting traction, rotary driving, clamping fixation and the like, and is important equipment for ensuring the smooth propulsion of wind measuring tower installation construction. In the existing wind measuring tower installation construction equipment, the problem that a winch traction structure for hoisting control is insufficient is caused, shaking is easy to occur in the hoisting process of a control mechanism, accurate handle control of space positions is difficult to achieve, meanwhile, the inclination angle adjusting mode of the control mechanism is limited in flexibility, obstruction is brought to alignment installation operation of an assembly frame, the matching design of a rotary driving part of the control mechanism and an assembly seat is unreasonable, the assembly frame installation position debugging process is long in time consumption, the position using requirements of different installation stations are difficult to adapt, reliable guiding and limiting structures are lacked, stability is insufficient when the assembly seat rotates and operates, the cooperative effect between parts for adjusting inclination angles in the clamping mechanism is poor, inclination angle adjustment of a clamping plate cannot be achieved accurately, the installation accuracy and the construction efficiency of the assembly frame are affected, meanwhile, the fixing structure design of a clamping module is deficient, loosening or shifting phenomenon easily occurs in the whole process of hoisting, azimuth debugging and angle adjusting of the assembly frame, and further the installation convenience and construction stability of the wind measuring tower are reduced, and the installation quality of the whole installation is influenced. Disclosure of Invention Aiming at the defects of the prior art, the invention provides wind measuring tower installation construction equipment, which solves the technical problems that the cooperative control of a traction structure of a winch under the lifting control is insufficient, so that shaking is easy to generate in the lifting process of a control mechanism, the space position is difficult to accurately control, the inclination angle adjustment mode of the control mechanism is limited in flexibility, the rotation driving part of the control mechanism is unreasonably matched with an assembly seat, the direction adjustment of the assembly frame is time-consuming, the stability is insufficient, the cooperative effect of the inclination angle adjustment part of the clamping mechanism is poor, and the fixing force of a clamping module is insufficient. The wind measuring tower installation construction equipment comprises a tower body, a balance arm, a linear movement module and a movable winch, wherein the balance arm is arranged on the upper end face of the tower body, the linear movement module is arranged at the bottom of the balance arm, the movable winch is arranged outside an output end of the linear movement module, the balance arm and the outside of the tower body are respectively connected with a first winch and a second winch, the bottom of the movable winch is provided with a control mechanism, two groups of control steel cables are respectively connected with the output ends of the first winch and the second winch, the movable winch is started to stably lift the control mechanism, meanwhile, the control steel cables are synchronously or asynchronously pulled through the first winch and the second winch, the whole space position of the control mechanism can be accurately controlled, the control mechanism is effectively prevented from rocking left and right in the lifting process, the inclination angle of the control mechanism can be flexibly adjusted, and convenience is provided for alignment installation of a worker on the wind measuring tower assembly frame; The utility model provides a control mechanism includes the roof, the inner chamber top of roof is provided with gear motor, gear motor's output is connected with fixed assembly seat, starts gear motor and can drive fixed assembly seat and rotate around the output to realize the debugging to the mount pad installation position fast, satisfy the position demand of different installation stations, fixed assembly seat's top is provided with protective housing and guide arm respectively, the track gro