The invention provides continuous gangue throwing and filling equipment for a coal mine roadway, which comprises a backfilling machine, a feeding machine, a reversed loader and a movable tail, wherein the backfilling machine is provided with a telescopic mechanism, a lifting mechanism, a rotary mechanism and a gangue throwing belt, the telescopic mechanism drives the gangue throwing belt to stretch back and forth, the lifting mechanism drives the gangue throwing belt to swing up and down, the rotary mechanism drives the gangue throwing belt to swing horizontally, the front end of the backfilling machine is provided with an auxiliary top connecting mechanism, the rear side of the backfilling machine is provided with a height adjusting and deflection adjusting mechanism and a supporting device, the lower side of the backfilling machine is provided with a travelling device, and the front side of the travelling device is provided with a push plate mechanism. The four-machine linkage continuous filling system is initiated, and pain points with low efficiency and high safety risk in the prior art are thoroughly solved. Continuous conveying and filling of gangue are realized through integrated linkage of a backfilling machine, a feeding machine, a reversed loader and a movable tail, continuous stepping of equipment can be realized through a self-walking mechanism, and small-step intermittent backward movement is not needed.

Inventors

  • DUAN JIANPING
  • WANG YANWU
  • Qiao Xianwen
  • YANG QI
  • Ke Shankun
  • SHAN YAN
  • CUI YONGPING

Assignees

  • 上海科煤机电设备制造有限公司

Dates

Publication Date
20260505
Application Date
20260331

Claims (10)

  1. 1. The continuous gangue throwing and filling equipment for the coal mine tunnel is characterized by comprising a backfilling machine (1), a feeding machine (2), a transfer machine (3) and a mobile tail (4), wherein a telescopic mechanism (103), a lifting mechanism (108), a slewing mechanism (110) and a gangue throwing belt (102) are arranged on the backfilling machine (1), the telescopic mechanism (103) drives the gangue throwing belt (102) to stretch back and forth, the lifting mechanism (108) drives the gangue throwing belt (102) to swing up and down, the slewing mechanism (110) drives the gangue throwing belt (102) to swing horizontally, an auxiliary roof-connecting mechanism (101) is arranged at the front end of the backfilling machine (1), a height-adjusting and deviation-adjusting mechanism (114) and a supporting device (115) are arranged at the rear side, a travelling device (107) is arranged at the lower side, and a push plate mechanism (106) is arranged at the front side of the travelling device (107).
  2. 2. The continuous waste rock throwing and filling equipment for the coal mine tunnel according to claim 1, wherein the auxiliary roof connecting mechanism (101) is formed by hinging a push shovel (10101) and a push shovel oil cylinder (10102), the height and deflection adjusting mechanism (114) is formed by a height adjusting platform (11401), supporting legs (11402) and a height adjusting oil cylinder (11403), the supporting device (115) is formed by supporting leg oil cylinders (11501) and rear supporting legs (11502), and the push plate mechanism (106) is formed by hinging a push plate (10601) and a push plate oil cylinder (10602).
  3. 3. The continuous gangue throwing and filling equipment for the coal mine tunnel according to claim 1, wherein the traveling device (107) is composed of a transmission device (10701), a track chain (10702) and a traveling frame (10703), a gangue throwing belt (102) of the backfilling machine (1) is further provided with a driving roller (111) and a receiving hopper (112), the receiving hopper (112) is in butt joint with a discharging end of the feeding machine (2), an operating table (104), a protective cover (105) and an electric cabinet (109) are arranged on the left side of the backfilling machine (1), and a hydraulic pump station and an oil tank (113) are arranged on the right side of the backfilling machine.
  4. 4. The continuous waste rock throwing and filling equipment for the coal mine tunnel according to claim 1 is characterized in that the feeding machine (2) comprises a waste rock blocking device (201) and a frame (203), a driving roller (202), a supporting wheel (204), a cable bracket (205), a trough type carrier roller (206), a horizontal carrier roller (207), a direction changing roller (209) and a guide rail (210) are arranged on the frame (203), a travelling device (107) with the same specification as the backfilling machine (1) is arranged on the lower side of the frame (203), a deflection mechanism (208) is arranged on the upper side of the travelling device (107), and the waste rock blocking device (201) consists of a lower waste rock blocking bucket (20101) and an upper waste rock blocking bucket (20102).
  5. 5. The continuous gangue throwing and filling equipment for the coal mine tunnel according to claim 4, wherein the deviation adjusting mechanism (208) is formed by hinging a supporting platform (20802) and a deviation adjusting oil cylinder (20801), and the deviation adjusting oil cylinder (20801) drives a frame (203) of the feeding machine (2) to horizontally swing to realize deviation adjustment.
  6. 6. The continuous waste rock throwing and filling equipment for the coal mine tunnel according to claim 1, wherein the reversed loader (3) comprises a side waste rock blocking plate (301) and a frame (203), a driving roller (202), a trough type carrier roller (206), a horizontal carrier roller (207) and a direction changing roller (209) are arranged on the frame (203), a travelling trolley (302) is arranged on the lower side of the frame (203), a supporting device (303) is arranged at the rear end of the travelling trolley, and the travelling trolley (302) is matched with a guide rail (210) of the feeding machine (2) and can travel back and forth along the guide rail (210).
  7. 7. The continuous waste rock throwing and filling equipment for the coal mine tunnel according to claim 6, wherein the supporting device (303) is composed of a supporting oil cylinder (30301), supporting feet (30302) and a guide post (30303), and the supporting oil cylinder (30301) drives the supporting feet (30302) to stretch up and down so as to stably support the reversed loader (3).
  8. 8. The continuous waste rock throwing and filling equipment for the coal mine tunnel according to claim 1 is characterized in that a traveling device (107) and a support (115) which are in the same specification as a backfilling machine (1) are arranged on the traveling device (4), the tail end of a reversed loader (3) is arranged on the traveling device (107), an operating platform (104), a protective cover (105) and an electric cabinet (109) are arranged on the left side of the traveling device (4), a hydraulic pump station and an oil tank (113) are arranged on the right side of the traveling device, a height and deflection adjusting mechanism (114) is arranged on the rear side of the traveling device, a feeding and unloading mechanism (401) and a cable storage frame (402) are arranged on the upper side of the height and deflection adjusting mechanism (114), and a deflection adjusting mechanism (208) is arranged on the lower side of the traveling device.
  9. 9. The continuous gangue throwing and filling equipment for the coal mine tunnel according to any one of claims 1 to 8, wherein the backfiller (1), the feeder (2), the reversed loader (3) and the mobile tail (4) support three control modes of local nearby control of an operating platform, remote control operation of a remote controller and remote centralized control, and can realize independent control of a single equipment or coordinated control of four machines.
  10. 10. A continuous waste rock throwing and filling method for a coal mine roadway adopting the equipment of any one of claims 1-8 is characterized by comprising three operation modes of back waste rock throwing and filling, front waste rock throwing and filling and back waste rock throwing and filling, wherein the back waste rock throwing and filling is that after an equipment system is in place, waste rock is conveyed to a backfiller (1) through a mobile tail (4), a transfer conveyor (3) and a loading machine (2), the waste rock throwing and filling is carried out to a region to be filled through a waste rock throwing belt (102), the waste rock throwing gesture is regulated through a telescopic, lifting and rotating mechanism, an auxiliary roof connecting mechanism (101) pushes and compacts the waste rock, the system synchronously continuously backs through a traveling device (107), the front waste rock throwing and filling is carried out to the region to be filled through the conveying link, the waste rock throwing and filling is carried out through the traveling device (107), and the front waste rock throwing and back waste rock filling is carried out synchronously continuously through the traveling device (107), and the front waste rock throwing and back waste rock filling is carried out to the full section through the front waste rock throwing and the back waste rock throwing and filling mode.

Description

Continuous gangue throwing and filling equipment and method for coal mine tunnel Technical Field The invention relates to the technical field of filling equipment, in particular to continuous gangue throwing and filling equipment and method for a coal mine roadway. Background With the current development of mine exploitation equipment to large-scale and mechanical, various resources are being exploited continuously from underground. Especially, a large amount of gangue generated during underground coal mining of a coal mine is required to be lifted and transported to the ground through the underground and then transported to a designated stacking area, and a 'gangue dump' is formed in daily accumulation and moon. The stacking mode not only occupies a large amount of land resources, but also often causes accidents such as spontaneous combustion, landslide and the like, so that serious environmental damage is caused, and tens of components such as S, P, C and the like contained in the gangue cause pollution to the atmosphere, water sources, soil and the like at different degrees, so that the living environment of human beings is seriously influenced. The gangue underground filling is a novel solution for the treatment and utilization of the gangue. By filling the coal gangue into the pit, not only limited coal resources can be replaced and ground subsidence can be reduced, but also the occupied land of gangue can be saved, and the pollution of dust, solid particles, harmful gas and spontaneous combustion heating to the surrounding environment can be eliminated, thereby realizing the comprehensive treatment of the coal gangue. Currently, the underground gangue filling equipment mainly comprises a gangue throwing device and a belt. Along with continuous filling of the gangue, the gangue conveying device needs to continuously move backwards at a smaller step distance, and meanwhile, the length of a conveying belt needs to be frequently adjusted, so that auxiliary procedures are more. If the operation is missed or the protective measures are not in place, the safety accident is easily caused, and the production efficiency is extremely low. In addition, the highest projection position of the filling operation in one step is basically fixed, the whole filling process is intermittent movement, so that the top of the gangue pile body is wavy and cannot be fully supported, the filling rate is low, and meanwhile, the filling operation requirement of a larger roadway section is difficult to meet due to structural limitation. In the prior art, 201810942021.3, a continuously filled gangue casting system, 201822236590.4, a mining gangue casting machine, 202321066130.6 and underground gangue casting complete equipment disclose a scheme of a basic split type filling device of a gangue casting device and a conveying belt, but the filling needs small steps of intermittent backward movement, the length of the belt is frequently adjusted, auxiliary procedures are multiple, the safety risk is high, the production efficiency is low, the casting position in a single step is fixed, the gangue is piled up in a wave shape, the top cannot be fully divided, the filling rate is low, the structure is limited, and the filling operation of a large-section roadway cannot be adapted. In addition, the system integration, exclusive structure, operation method and control scheme are not disclosed in the prior art. Disclosure of Invention The technical problem to be solved by the invention is to provide continuous gangue throwing and filling equipment and method for coal mine roadways, which solve the problems that the existing gangue filling equipment is low in production efficiency, cannot fully support the top, and has insufficient adaptability to large-section roadways. In order to solve the technical problems, the invention provides the following technical scheme: The continuous gangue throwing and filling equipment for the coal mine tunnel comprises a backfilling machine, a feeding machine, a reversed loader and a movable tail, wherein a telescopic mechanism, a lifting mechanism, a rotary mechanism and a gangue throwing belt are arranged on the backfilling machine, the telescopic mechanism drives the gangue throwing belt to stretch back and forth, the lifting mechanism drives the gangue throwing belt to swing up and down, the rotary mechanism drives the gangue throwing belt to swing horizontally, an auxiliary top connecting mechanism is arranged at the front end of the backfilling machine, a height-adjusting and deflection-adjusting mechanism and a supporting device are arranged at the rear side of the backfilling machine, a running gear is arranged at the lower side of the backfilling machine, and a push plate mechanism is arranged at the front side of the running gear. Further, the auxiliary top connecting mechanism is formed by hinging a push shovel with a push shovel oil cylinder, the height-adjusting and deviation-adjusting mechanism i