CN-121981429-A - Method, device and storage medium for determining material delivery time
Abstract
The application relates to the field of logistics distribution in production workshops in engineering machinery industry, and discloses a method, a device and a storage medium for determining material distribution time, wherein the method comprises the steps of determining second procedures with configuration beats with a first procedure under the condition that the first procedure triggers a passing point signal, and determining beat time between the first procedure and the second procedure according to the type of the passing point signal aiming at each second procedure; the method comprises the steps of determining a predicted starting time point of each second procedure based on a sending time point and beat time length of a passing point signal, determining a material distribution time point of each second procedure according to the predicted starting time point of each second procedure, and determining a material warehouse sorting time point of each second procedure according to the material distribution time point of each second procedure.
Inventors
- KANG XI
- ZHU DONGPING
- REN ZIYI
- TANG XINGYU
- YIN PENGJUN
- YE MENG
Assignees
- 中科云谷科技有限公司
Dates
- Publication Date
- 20260505
- Application Date
- 20251211
Claims (13)
- 1. A method for determining material delivery time, the method comprising: Determining a second procedure with a configuration beat to the first procedure under the condition that the first procedure triggers a passing point signal, wherein the configuration beat represents a certain correlation between a material distribution time point of the second procedure and a sending time point of the passing point signal, and the passing point signal is generated when the first procedure is started or the first procedure is finished; For each second procedure, determining a beat duration P between the first procedure and the second procedure according to the type of the passing point signal; For each second procedure, determining a predicted starting time point of the second procedure based on the sending time point of the passing point signal and the beat time length P; determining the material dispensing time point of each second procedure according to the predicted starting time point of each second procedure; And determining the time point when the material warehouse of each second procedure should sort according to the time point when the material of each second procedure should be distributed.
- 2. The method for determining material delivery time of claim 1, further comprising: triggering an initial passing point signal under the condition that a start-up instruction is acquired; determining the latest material distribution time point for the first procedure according to the generation time point of the initial passing point signal; And controlling the material distribution operation aiming at the first working procedure according to the latest material distribution time point.
- 3. The method for determining material delivery time of claim 1, further comprising: For any one second procedure, under the condition that a plurality of first procedures exist before the second procedure, continuously determining the material distribution time point of the second procedure and/or the sorting time point of a material warehouse according to the sending time point of the passing point signal of each first procedure; Setting the material distribution time point and/or the material warehouse sorting time point which are determined based on the latest passing point signal as invalid under the condition that the obtained material distribution time point and/or the material warehouse sorting time point are determined according to the latest passing point signal and are later than the effective time point calculated last time; and determining the material dispensing time point of the second procedure and/or the material warehouse sorting time point according to the time point of the last passing point signal.
- 4. A method for determining a material delivery time as claimed in claim 3, further comprising: In the case that the material dispensing time point and/or the material warehouse sorting time point determined based on the latest passing point signal is earlier than the effective time point calculated last time but later than the current time point, the material dispensing time point and/or the material warehouse sorting time point determined based on the latest passing point signal is set to be effective.
- 5. A method for determining a material dispensing time according to claim 1, wherein for each second process step determining a beat length P between the first process step and the second process step based on the type of the over-point signal comprises: determining the number of working procedures between the first working procedure and the second working procedure, and determining the type of materials required for each working procedure in the middle and the material distribution time of each material; and determining the beat time length P between the first working procedure and the second working procedure according to the number of working procedures, the type of materials needed by each working procedure and the material distribution time length of each material.
- 6. The method for determining material dispensing time according to claim 1, wherein determining a predicted start-up time point of the second process based on the emission time point of the passing point signal and the beat time length P comprises, for each second process: And determining the predicted starting time point of the second procedure according to the sending time point of the passing point signal and the beat time length P.
- 7. A method for determining a material dispensing time as claimed in claim 1 wherein determining the material dispensing time for each second process based on the predicted start-up time for each second process comprises: determining the type of the material required by each second procedure, and determining the theoretical material delivery time required to be consumed for delivering each material to the position of each second procedure; And determining the material dispensing time point of each second process according to the predicted starting time point and the material theoretical dispensing time length of each second process.
- 8. The method for determining a material dispensing time of claim 1, wherein determining a material warehouse picking time point for each second process based on the material dispensing time point for each second process comprises: And determining the time point when the material warehouse of each second procedure is required to sort according to the material distribution time point of each second procedure and the material theoretical sorting time length of each second procedure, wherein the material sorting time length of each second procedure refers to the time from the beginning of sorting to the completion of sorting of the raw materials of each second procedure.
- 9. The method for determining material delivery time of claim 1, further comprising: And setting a first procedure associated with each second procedure according to the association between different procedures, wherein the first procedures associated with the different second procedures can be different.
- 10. The method for determining material delivery time of claim 1, further comprising: after determining the time point when the material warehouse of each second procedure should sort according to the time point when the material of each second procedure should be distributed, determining the first actual starting point of each second procedure according to the time point when the material warehouse of each procedure should sort, the actual sorting time length of the material and the actual distribution time length of the material; and adjusting the type of the passing point signal on which the second procedure depends or the associated first procedure when the first actual starting point is later than the predicted starting point.
- 11. The method for determining material delivery time of claim 1, further comprising: After determining a predicted start time point of the second process based on the emission time point of the passing point signal and the beat time length P, comparing the predicted start time point with a second actual start time point of the second process; and re-determining the type of the passing point signal associated with the second working procedure or the first working procedure depending on the second actual working procedure based on the second actual working procedure time point when the predicted working procedure time point is earlier than the second actual working procedure time point.
- 12. An apparatus for determining material delivery time, comprising: a memory configured to store instructions; A processor configured to invoke the instructions from the memory and when executing the instructions is capable of implementing the method for determining material delivery time according to any of claims 1 to 11.
- 13. A machine-readable storage medium having instructions stored thereon, which when executed by a processor cause the processor to be configured to perform the method for determining material delivery time according to any of claims 1 to 11.
Description
Method, device and storage medium for determining material delivery time Technical Field The application belongs to the field of warehouse logistics, and particularly relates to a method, a device and a storage medium for determining material distribution time. Background In the discrete manufacturing industry, especially in the production of assembly lines of automobiles, engineering machinery and the like, the on-time distribution of materials is a key for ensuring the production beat and improving the production efficiency. The production line needs to receive raw materials or parts required for subsequent processes at an appropriate time point according to a given production tact. Too late delivery can lead to material shortage and shutdown of the production line, and huge economic loss is caused. At present, many manufacturing enterprises still adopt a traditional material distribution scheduling mode, namely, production line workers, distribution staff and storage staff perform downlink communication to finish material distribution and online. However, the method has high manual requirements, and has the problems of large material distribution time estimated deviation, slow information transmission between a production line and a storage department, a distribution department and the like, and cannot meet the high-efficiency intelligent automatic production requirements of enterprises. Specifically, the material distribution mode using the manual communication as the core has two inherent defects that firstly, the distribution time calculation deviation is large, and the production stability is influenced. The calculation of material distribution time completely depends on personal experience of production line workers, but the production process has a plurality of variables, such as short equipment halt, time delay of a previous procedure, fluctuation of personnel operation efficiency and the like, so that manual estimation is difficult to accurately, line side congestion, material management confusion or production line halt waiting can be caused by calculation deviation, the continuity and stability of production are damaged, and the information transmission chain is long and low in efficiency, and cannot respond to production change in real time. The information transmission mode relying on manual communication is slow and low in speed and efficiency from a production line to a warehouse to a distribution link, when the production beat is dynamically adjusted or abnormal conditions occur, the information cannot be timely and accurately fed back to a logistics link, so that logistics scheduling and actual production demands are disjointed, distribution instructions are often based on outdated or distorted information, and the requirements of flexible production and quick response cannot be met. Disclosure of Invention The application aims to provide a method, a processor and a storage medium for determining material delivery time. To achieve the above object, an aspect of the present application provides a method for determining a material dispensing time, including: determining a second procedure with a configuration beat with the first procedure under the condition that the first procedure triggers the passing point signal, wherein the configuration beat represents a certain correlation between a material distribution time point of the second procedure and a sending time point of the passing point signal, and the passing point signal is generated when the first procedure is started or the first procedure is finished; for each second procedure, determining the beat time length P between the first procedure and the second procedure according to the type of the passing point signal; For each second procedure, determining a predicted starting time point of the second procedure based on the sending time point of the passing point signal and the beat time length P; determining the material dispensing time point of each second procedure according to the predicted starting time point of each second procedure; And determining the time point when the material warehouse of each second procedure should sort according to the time point when the material of each second procedure should be distributed. The method for determining the material distribution time further comprises the steps of triggering an initial passing point signal under the condition that a start command is acquired, determining the material latest distribution time point for the first working procedure according to the generation time point of the initial passing point signal, and controlling material distribution operation for the first working procedure according to the material latest distribution time point. In the embodiment of the application, the method for determining the material distribution time further comprises the steps of continuously determining the material distribution time point and/or the material warehouse sorting time poi