CN-121992947-A - Inter-building special-shaped overlapped steel structure corridor installation construction method
Abstract
The invention discloses a method for installing and constructing inter-building special-shaped overlapped steel structure galleries, belongs to the technical field of installing and constructing steel structure galleries, and solves the problem that the existing steel structure galleries are not suitable for constructing multi-layer overlapped galleries; the hydraulic synchronous lifting system is installed on a lifting platform, a high-rise steel structure corridor main frame and a low-rise steel structure corridor are assembled, the high-rise steel structure corridor main frame is lifted to a specified height, partial components which are not overlapped with the low-rise steel structure corridor in the vertical direction on the high-rise steel structure corridor main frame are installed, the low-rise steel structure corridor is lifted to the specified height, and other components are installed on the high-rise steel structure corridor main frame. In the invention, the main assembly, welding and other works of the high-rise steel structure corridor main frame and the low-rise steel structure corridor are carried out on the ground, and the parts can be hoisted by using an automobile crane, so that the construction efficiency is high, the construction quality is easy to ensure, the high-altitude hoisting workload can be reduced to the greatest extent, and the installation and construction period is shortened.
Inventors
- CHE JIN
- ZHENG HAOTENG
- XIONG FANHUI
- YANG HONGWEI
- HU SHUZHI
- ZHANG YU
Assignees
- 中建一局集团华南建设有限公司
- 深圳市龙华安居有限公司
Dates
- Publication Date
- 20260508
- Application Date
- 20260114
Claims (6)
- 1. The construction method for installing the inter-building special-shaped overlapped steel structure corridor is characterized by comprising the following steps of: Step S1, installing a high-layer preassembly structure (3) and a low-layer preassembly structure (4) at corresponding positions on a shear wall; Step S2, arranging a high-rise lifting platform (6) and a low-rise lifting platform (7), and respectively installing a hydraulic synchronous lifting system (5) on the high-rise lifting platform (6) and the low-rise lifting platform (7); S3, assembling a main frame of the high-rise steel structure corridor (1), lifting to 2-4 meters, and suspending; S4, splicing the lower-layer steel structure corridor (2); step S5, continuously lifting the main frame of the high-rise steel structure corridor (1) to a specified height, and installing partial members, which are not overlapped with the low-rise steel structure corridor (2) in the vertical direction, on the main frame of the high-rise steel structure corridor (1); Step S6, lifting the low-layer steel structure corridor (2) to a specified height; And S7, installing other components on the main frame of the high-rise steel structure corridor (1).
- 2. The method for installing and constructing the inter-building special-shaped overlapped steel structure corridor according to claim 1, wherein the step S3 includes: Step 301, arranging a steel structure corridor pre-assembly supporting device on a skirt house roof, and assembling a main frame of the high-rise steel structure corridor (1) under a projection plane of an installation position of the high-rise steel structure corridor (1); And S302, welding a temporary lifting appliance (53) on the main frame of the high-rise steel structure corridor (1), and suspending after lifting the main frame of the high-rise steel structure corridor (1) by 2-4 meters by utilizing a hydraulic synchronous lifting system (5) on a high-rise lifting platform (6).
- 3. The method for installing and constructing the inter-building profiled overlapping steel structure corridor according to claim 2, wherein the step S4 includes: s401, splicing a main frame of the low-rise steel structure corridor (2) at a position right below a projection plane of the installation position of the low-rise steel structure corridor (2), wherein a part of the low-rise steel structure corridor (2) and the high-rise steel structure corridor (1) overlapped in the vertical direction passes through a gap of the main frame of the high-rise steel structure corridor (1) by utilizing a tower crane to splice; step S402, mounting rear repair pieces on a main frame of the low-rise steel structure corridor (2) after assembly and welding; And S403, paving a floor support plate and decorating to form the complete low-layer steel structure corridor (2).
- 4. The method for installing and constructing the inter-building profiled overlapping steel structure corridor according to claim 3, wherein the step S5 includes: Step S501, continuously lifting the main frame of the high-rise steel structure corridor (1) to a set height by utilizing a hydraulic synchronous lifting system (5) on the high-rise lifting platform (6), and butting with the upper preassembly structure; Step S502, unloading each lifting point of the hydraulic synchronous lifting system (5) on the high-rise lifting platform (6) in sequence, so that the self weight of the main frame of the high-rise steel structure corridor (1) is transferred to a preassembled structure to reach a design state; And S503, mounting a rear compensation member and a floor support plate at a position which is not overlapped with the lower layer steel structure corridor (2) on the main frame of the higher layer steel structure corridor (1).
- 5. The method for installing and constructing the inter-building profiled overlapping steel structure corridor according to claim 4, wherein the step S6 includes: step S601, welding a temporary lifting appliance (53) on a lower-layer steel structure corridor (2); step S602, lifting the low-layer steel structure corridor (2) to a designated height by utilizing a hydraulic synchronous lifting system (5) on a low-layer lifting platform (7), so that the low-layer steel structure corridor (2) is in butt joint with an upper preassembly structure to form a whole; And S603, unloading the hydraulic synchronous lifting system (5) on the low-layer lifting platform (7) to transfer the self weight of the main frame of the low-layer steel structure corridor (2) to the preassembled structure.
- 6. The method for installing and constructing the inter-building profiled overlapping steel structure corridor according to claim 5, wherein the step S7 includes: Step 701, installing a rear compensation member at the overlapping position with the lower-layer steel structure corridor (2) on the main frame of the higher-layer steel structure corridor (1), and welding; and step 701, paving the rest floor support plates in the neutral area and decorating to form the complete high-rise steel structure corridor (1).
Description
Inter-building special-shaped overlapped steel structure corridor installation construction method Technical Field The invention relates to the technical field of steel structure corridor installation construction, in particular to an inter-building special-shaped overlapped steel structure corridor installation construction method. Background With the continuous development of high-rise building construction, the steel structure is widely applied due to the advantages of high strength, light dead weight, short construction period and the like. In high-rise buildings, steel structure corridors are often used to connect different towers to achieve the integrity of building functions. However, in the traditional steel structure installation and corridor construction process, the problems of high overhead workload and high safety risk exist, component hoisting depends on large equipment, is limited by the site and equipment performance, has low construction efficiency, is difficult to control the installation precision of embedded parts and the butting precision of components, influences the structural stability, and has high erection difficulty of assembled jig frames and outstanding quality and safety risk when the corridor parts are in high-altitude bulk. Because steel construction vestibule installation belongs to high altitude construction, if adopt the high altitude bulk packing of branch, not only high altitude equipment, welding work load are big, and on-the-spot mechanical equipment also hardly satisfies the hoist and mount requirement, and the assembly jig frame of required high altitude is difficult to set up moreover, has very big safety, quality risk. The construction difficulty is high, and the safety, quality and construction period control of the steel structure on-site installation are not facilitated. Therefore, the steel structure corridor is assembled in advance in the prior art, and then the assembled steel structure corridor is lifted to the designated height by the lifting equipment. This mode of operation is less difficult to implement for single-layer or simple-structure steel construction galleries. But to high-rise building, often there is the steel construction vestibule of high floor and the steel construction vestibule of low floor to have the phenomenon of overlapping in vertical direction, and this kind of overlapping vestibule structure is because the vestibule of low floor can influence the promotion of high-rise vestibule, and consequently the construction degree of difficulty is big, and the efficiency of construction is low. Disclosure of Invention Aiming at the defects in the prior art, the invention provides a method for installing and constructing a special-shaped overlapped steel structure corridor among buildings, which solves the problem that the existing steel structure corridor construction method is not suitable for constructing a multi-layer overlapped corridor. In order to achieve the above purpose, the invention adopts the following technical scheme: step S1, mounting a high-layer preassembled structure and a low-layer preassembled structure at corresponding positions on a shear wall; step S2, setting a high-rise lifting platform and a low-rise lifting platform, and respectively installing a hydraulic synchronous lifting system on the high-rise lifting platform and the low-rise lifting platform; s3, assembling a main frame of the high-rise steel structure corridor, lifting to 2-4 meters, and suspending; S4, splicing and assembling the low-layer steel structure corridor; step S5, continuously lifting the main frame of the high-rise steel structure corridor to a designated height, and installing partial members, which are not overlapped with the low-rise steel structure corridor in the vertical direction, on the main frame of the high-rise steel structure corridor; Step S6, lifting the low-layer steel structure corridor to a designated height; and S7, installing other components on the main frame of the high-rise steel structure corridor. In the scheme, the main assembly, welding and other works of the high-rise steel structure corridor main frame and the low-rise steel structure corridor are carried out on the ground, the automobile crane can be used for hoisting parts, the construction efficiency is high, the construction quality is easy to ensure, part of components of the high-rise steel structure corridor main frame are hoisted in the high air, the high-rise hoisting workload can be reduced to the greatest extent, and the installation and construction period is shortened. Further, step S3 includes: step 301, arranging a steel structure corridor pre-assembly supporting device on a skirt house roof, and assembling a high-rise steel structure corridor main frame at a position right below a projection plane of a high-rise steel structure corridor installation position; And S302, welding a temporary lifting appliance on the main frame of the high-rise steel struct