CN-121998265-A - Box-type building data processing method and device, electronic equipment and medium
Abstract
The application relates to the technical field of data processing, in particular to a box-type building data processing method, device, electronic equipment and medium. The method comprises the steps of obtaining construction area information, determining target building area information based on the construction area information, wherein the construction area information is area information with construction requirements, the target building area information is an area where a box-type building needs to be placed, obtaining building unit information, determining a target building unit according to the target building area information and the building unit information, determining a building unit placement position based on the target building area information and the target building unit, determining a placement scheme if the building unit placement position is successfully matched with a preset building unit position, and feeding back for display. The application can reduce the error of manual input and improve the efficiency of box-type building construction.
Inventors
- YOU DEQIANG
- XU SHUNWEI
- YANG MOHAN
- YUAN JIANGPING
- JING YONGQIAN
Assignees
- 江门中集数字能源装备有限公司
Dates
- Publication Date
- 20260508
- Application Date
- 20240201
Claims (10)
- 1. A box-based construction data processing method, comprising: acquiring construction area information, and determining target building area information based on the construction area information, wherein the construction area information is area information with construction requirements, and the target building area information is an area where a box-type building needs to be placed; Building unit information is acquired, and a target building unit is determined according to the target building area information and the building unit information; determining a building unit placement location based on the target building area information and the target building unit; if the building unit placement position is successfully matched with the preset building unit position, determining a placement scheme and feeding back for display.
- 2. The box-based construction data processing method according to claim 1, wherein the determining target construction area information based on the construction area information comprises: Determining construction environment information based on the construction area information; determining construction planning information based on the construction environment information; determining building area information according to the construction planning information; And if the building area information is consistent with a preset building area threshold value, determining the building area information as target building area information.
- 3. The box-based construction data processing method according to claim 2, wherein the determining construction environment information further comprises: determining construction difficulty information according to construction environment information; And determining the construction time based on the construction difficulty information.
- 4. The box-based construction data processing method according to claim 1, wherein the determining a target construction unit based on the target construction area information and the construction unit information comprises: Determining building space information based on the target building area information; matching the building space information with building unit information; and if the building space information is successfully matched with the building unit information, determining the building unit as a target building unit.
- 5. The box-based construction data processing method according to claim 1, wherein the determining a construction unit placement position based on the target construction area information and the target construction unit comprises: determining the number of building unit layers based on the target building area information; Determining the arrangement sequence of building units according to the number of layers of the building units; and determining the building unit placement position based on the building unit placement sequence and the target building unit.
- 6. The box-based construction data processing method according to claim 1, wherein the determining a placement scheme includes: Acquiring engineering quantity information and building material information; Splitting the engineering quantity information and the building material information to obtain sub-engineering quantity information and sub-building material information; Determining a first keyword based on the sub-engineering quantity information; Determining a second keyword based on the sub-building material information; If the first keyword is successfully matched with the second keyword, determining engineering cost information; based on the engineering cost information, a placement scheme is determined.
- 7. The box-based construction data processing method according to claim 6, wherein the determining construction cost information comprises: acquiring a preset table; Determining a third keyword based on the preset table; Identifying the third keywords, and determining category information corresponding to the third keywords; And determining engineering cost information based on the category information.
- 8. A box-based building data processing apparatus, comprising: The building construction system comprises a regional information determining module, a building information processing module and a building information processing module, wherein the regional information determining module is used for acquiring construction regional information, determining target building regional information based on the construction regional information, wherein the construction regional is regional information with construction requirements, and the target building regional information is a region in which a box-type building needs to be placed; The target building unit determining module is used for acquiring building unit information and determining a target building unit according to the target building area information and the building unit information; a placement position determination module for determining a building unit placement position based on the target building area information and the target building unit; and the feedback module is used for determining a placement scheme and feeding back and displaying if the placement position of the building unit is successfully matched with the preset building unit position.
- 9. An electronic device, characterized in that, the electronic device includes: at least one processor; A memory; at least one application program stored in the memory and configured to be executed by the at least one processor, the at least one application program configured to perform a box-based construction data processing method of any one of claims 1-7.
- 10. A computer-readable storage medium, on which a computer program is stored, characterized in that the computer program, when executed in a computer, causes the computer to perform a box-based construction data processing method according to any one of claims 1 to 7.
Description
Box-type building data processing method and device, electronic equipment and medium Technical Field The application relates to the technical field of data processing, in particular to a box-type building data processing method, device, electronic equipment and medium. Background With the development of modern technology, the data processing requirements for box-type buildings are increasing. The box-type building has the characteristics of integration, modularization and high efficiency and flexibility, but has a plurality of problems in the aspect of subsequent processing of data collection, so how to process the data of the box-type building is also a problem to be solved at present. The traditional box-type building data processing method mainly comprises manual collection and manual analysis, and a conclusion is obtained by manually carrying out analysis and comparison through field investigation or through historical data. However, since the conventional and conventional box-type building data processing method requires manual intervention and adjustment, inaccuracy of data may occur when box-type building data is manually entered, and an accurate construction scheme cannot be determined directly through the box-type data and the requirements of construction sites. Disclosure of Invention In order to reduce errors of manual input and improve efficiency of box-type building construction, the application provides a box-type building data processing method, device, electronic equipment and medium. In a first aspect, the present application provides a method for processing data based on a box-type building, which adopts the following technical scheme: A box-based building data processing method, comprising: acquiring construction area information, and determining target building area information based on the construction area information, wherein the construction area information is area information with construction requirements, and the target building area information is an area where a box-type building needs to be placed; Building unit information is acquired, and a target building unit is determined according to the target building area information and the building unit information; determining a building unit placement location based on the target building area information and the target building unit; if the building unit placement position is successfully matched with the preset building unit position, determining a placement scheme and feeding back for display. By adopting the technical scheme, after construction area information is acquired, the area where the box type building is required to be placed, namely target building area information is determined according to analysis of the construction area information, the area where the construction is required to be performed is determined more accurately, building unit information is acquired, specific information of building units is obtained, the target building units are determined through matching of the target building area and the building unit information, building units meeting construction standards and meeting customer requirements are determined, then the target building units are arranged and combined according to the target building area information, the building unit placement position corresponding to each building unit is determined, if the building unit placement position is successfully matched with the preset building unit position, the building unit placement position meets the construction standards and meets the customer requirements, then the corresponding placement scheme is determined according to the building unit placement position, and feedback display is carried out, so that the efficiency of box type building construction is improved while errors of manual input are reduced. In one possible implementation manner, the determining the target building area information based on the construction area information includes: Determining construction environment information based on the construction area information; determining construction planning information based on the construction environment information; determining building area information according to the construction planning information; And if the building area information is consistent with a preset building area threshold value, determining the building area information as target building area information. By adopting the technical scheme, the construction environment information is determined through identifying the construction area information, so that the characteristics and the requirements of the construction area are better known and mastered, then, the construction planning information corresponding to the construction environment information is obtained based on the construction environment information, so that reasonable and feasible construction planning is formulated, the construction area information is obtained according to the construction plan