CN-122026613-A - Transmission section generation method and device, storage medium and computer equipment
Abstract
According to the power transmission section generation method, the device, the storage medium and the computer equipment, provided by the application, the equipment set influenced by the change and the active power of each equipment are determined by detecting the change of the grid structure of the power grid in real time, so that the power transmission section range needing to be adjusted is accurately locked. And then determining at least one pre-constructed power transmission section based on the equipment set, and further calculating the limit value and the control value of each pre-constructed power transmission section after the medium adjustment index and the effective time of each pre-constructed power transmission section are determined. So as to ensure that the section definition is accurately matched with the current operation mode and avoid the monitoring failure problem. And generating and checking the transmission section data file based on the determined data, and transmitting the transmission section data file to a safe area when the checking is passed. The process replaces the traditional manual configuration by automatic closed-loop processing, so that the risk of manual update lag and misoperation is eliminated, and the accuracy of section calculation is ensured by standardized data auditing.
Inventors
- CHEN Jin
- LIN JINPEI
- DENG ZHIGUANG
- YAO RUOHAO
- PENG CHENG
- HUANG FUYING
- LING XIN
- ZHOU JINGYANG
Assignees
- 广东电网有限责任公司佛山供电局
Dates
- Publication Date
- 20260512
- Application Date
- 20260127
Claims (10)
- 1. A power transmission section generation method, characterized in that the method comprises: When the change of the grid structure is detected, determining a device set influenced by the change and the active power of each device in the device set; Determining at least one pre-constructed power transmission section based on the equipment set, and calculating a threshold value and a control value of each pre-constructed power transmission section according to each pilot adjustment index after the pilot adjustment index and the effective time of each pre-constructed power transmission section are determined; Generating a transmission section data file based on the active power of each device in the device set, the medium adjustment index, the limit value, the control value and the effective time of each pre-constructed transmission section; And carrying out data auditing on the power transmission section data file, and transmitting the power transmission section data file to a safe first area when the auditing is passed so as to construct a corresponding power transmission section based on the power transmission section data file in the safe first area.
- 2. The power transmission section generation method according to claim 1, wherein the determining the set of devices affected by the change and the active power of each device in the set of devices includes: Evaluating the influence degree of the change on the equipment contained in each key section in the power grid, and determining the equipment with the influence degree reaching the expected degree as target equipment; and forming a device set according to the determined target devices, and acquiring the active power of each device in the device set.
- 3. The power transmission section generation method according to claim 1, wherein the determining at least one pre-constructed power transmission section based on the set of devices comprises: analyzing the electrical connection relation among all the devices in the device set based on the power grid topological structure so as to identify the device combination meeting the preset electrical coupling condition; And determining a pre-constructed power transmission section according to each equipment combination respectively so as to obtain at least one pre-constructed power transmission section.
- 4. The method for generating a power transmission section according to claim 1, wherein after determining the medium adjustment index and the effective time of each pre-constructed power transmission section, calculating the threshold value and the control value of each pre-constructed power transmission section according to the medium adjustment index, comprises: For each pre-constructed power transmission section, determining the effective time of the power transmission section according to the type of the detected grid structure change, and acquiring the line scale and the main transformer scale of equipment contained in the power transmission section; Determining a medium adjustment index of the power transmission section according to the line scale and the main transformer scale; Obtaining a first preset proportion and a second preset proportion, calculating an out-of-limit value of the power transmission section according to the first preset proportion and the medium adjustment index, and calculating a control value of the power transmission section according to the second preset proportion and the medium adjustment index.
- 5. The power transmission section generation method according to claim 1, wherein the generating a power transmission section data file based on the active power of each device in the device set, the medium adjustment index, the threshold value, the control value, and the effective time of each pre-constructed power transmission section includes: acquiring a preset section format template; And respectively filling the active power of each device in the device set, the medium adjustment index, the threshold value, the control value and the effective time of each pre-constructed power transmission section into the corresponding positions of the section format template to obtain a power transmission section data file.
- 6. The power transmission section generation method according to any one of claims 1 to 5, wherein the data auditing the power transmission section data file includes: Carrying out integrity check on the power transmission section data file, and if the integrity check is passed, carrying out static security check on the power transmission section data file based on a preset power grid simulation platform; when the transmission section data file passes static security check, the transmission section data file is considered to pass check; and if the integrity check is not passed or the static security check is not passed, the transmission section data file audit is considered to be not passed.
- 7. The power transmission section generation method according to claim 1, characterized in that the method further comprises: And when the data auditing is not passed, generating a corresponding prompt according to the data auditing result, and sending the prompt.
- 8. A power transmission section generating apparatus, characterized by comprising: the information determining module is used for determining a device set influenced by the change and the active power of each device in the device set when the change of the grid structure is detected; The data calculation module is used for determining at least one pre-constructed power transmission section based on the equipment set, calculating the limit value and the control value of each pre-constructed power transmission section according to each pilot tone index after the pilot tone index and the effective time of each pre-constructed power transmission section are determined; The file generation module is used for generating a power transmission section data file based on the active power of each device in the device set, the medium adjustment index, the limit value, the control value and the effective time of each pre-constructed power transmission section; And the file auditing module is used for conducting data auditing on the power transmission section data file, and transmitting the power transmission section data file to a safe first area when the auditing passes so as to construct a corresponding power transmission section based on the power transmission section data file in the safe first area.
- 9. A storage medium having stored therein computer readable instructions which, when executed by one or more processors, cause the one or more processors to perform the steps of the power transmission section generation method of any one of claims 1 to 7.
- 10. A computer device includes one or more processors and a memory; stored in the memory are computer readable instructions which, when executed by the one or more processors, perform the steps of the power transmission profile generation method of any one of claims 1 to 7.
Description
Transmission section generation method and device, storage medium and computer equipment Technical Field The present application relates to the field of power grid monitoring technologies, and in particular, to a method and apparatus for generating a power transmission section, a storage medium, and a computer device. Background In the operation of a power system, a power transmission section is an important index reflecting the operation state of a key power transmission channel of a power grid, and is generally composed of active power of a main transformer and active power of a line. Because of the strong electric connection transmission links in the power grid, if the key sections are disconnected due to faults, chain reactions such as voltage out-of-limit, frequency oscillation and even system disconnection can be caused, and large-area power failure accidents can be caused. Therefore, the operation mode department needs to formulate a power transmission section and an alarm value thereof according to the actual structure of the power grid, and realizes real-time monitoring through a dispatching automation system. However, the management of the current power transmission section is highly dependent on manual maintenance, when the grid structure of the power grid changes, an automatic operation and maintenance personnel needs to manually establish a calculation point, associated equipment data in a database and update a section table, and the process is low in efficiency and difficult to ensure timeliness and accuracy of updating the power transmission section data. Disclosure of Invention The application aims to at least solve one of the technical defects, and particularly the technical defects that in the prior art, when the grid structure of a power grid is changed, an automatic operation and maintenance personnel needs to manually establish calculation points and associated equipment data in a database and update a section table, the process is low in efficiency, and timeliness and accuracy of updating the power transmission section data are difficult to ensure. In a first aspect, the present application provides a method for generating a power transmission section, the method including: When the change of the grid structure is detected, determining a device set influenced by the change and the active power of each device in the device set; Determining at least one pre-constructed power transmission section based on the equipment set, and calculating a threshold value and a control value of each pre-constructed power transmission section according to each pilot adjustment index after the pilot adjustment index and the effective time of each pre-constructed power transmission section are determined; Generating a transmission section data file based on the active power of each device in the device set, the medium adjustment index, the limit value, the control value and the effective time of each pre-constructed transmission section; And carrying out data auditing on the power transmission section data file, and transmitting the power transmission section data file to a safe first area when the auditing is passed so as to construct a corresponding power transmission section based on the power transmission section data file in the safe first area. In one embodiment, the determining the set of devices affected by the change and the active power of each device in the set of devices includes: Evaluating the influence degree of the change on the equipment contained in each key section in the power grid, and determining the equipment with the influence degree reaching the expected degree as target equipment; and forming a device set according to the determined target devices, and acquiring the active power of each device in the device set. In one embodiment, the determining at least one pre-constructed power transmission section based on the set of devices includes: analyzing the electrical connection relation among all the devices in the device set based on the power grid topological structure so as to identify the device combination meeting the preset electrical coupling condition; And determining a pre-constructed power transmission section according to each equipment combination respectively so as to obtain at least one pre-constructed power transmission section. In one embodiment, after determining the medium adjustment index and the effective time of each pre-constructed power transmission section, calculating the threshold value and the control value of each pre-constructed power transmission section according to each medium adjustment index, including: For each pre-constructed power transmission section, determining the effective time of the power transmission section according to the type of the detected grid structure change, and acquiring the line scale and the main transformer scale of equipment contained in the power transmission section; Determining a medium adjustment index of the power transm