CN-224200175-U - Sliding device for installing roof large-span daylighting roof steel girder
Abstract
The utility model discloses a sliding device for installing a roof large-span daylighting roof steel beam, and belongs to the field of construction equipment. The device comprises two sliding units for moving the steel beam, wherein each sliding unit comprises a distribution beam, a sliding structure and a weight piece. In the sliding structure, two main frames are arranged at intervals in parallel, and detachable connecting rods are vertically arranged between the main frames. One side of the main frame is provided with a weight platform for placing the weight. The top of the main frame is detachably connected with one end of the distribution beam, and the other end of the distribution beam is provided with a through bolt for connecting with the steel beam. The supporting rods are detachably arranged between the weight platform and the distribution beam. The girder steel spanned daylighting top entrance to a cave, through the unit that slides that sets up at girder steel both ends, transported the girder steel to required mounted position. The device simple structure, simple operation can effectively promote the efficiency of construction, ensure the security and the stability of installation simultaneously.
Inventors
- LU YU
- WANG JUN
- XU HAN
- YE SIYU
- LIANG CHENGJIANG
Assignees
- 浙江中天恒筑建筑科技有限公司
Dates
- Publication Date
- 20260505
- Application Date
- 20250407
Claims (9)
- 1. The sliding device for installing the roof large-span daylighting roof steel girder is characterized by comprising two sliding units for moving the steel girder (4), wherein each sliding unit comprises a distribution beam (1), a sliding structure (2) and a counterweight (3); The sliding structure (2) comprises a main frame (2-1), connecting rods (2-2), a weight platform (2-3) and supporting rods (2-4), wherein the main frame (2-1) is arranged in two, the main frames (2-1) are arranged at intervals in parallel, the detachable connecting rods (2-2) are vertically arranged between the two main frames (2-1), the weight platform (2-3) used for placing weight pieces (3) is arranged on one side of the main frame (2-1), the top of the main frame (2-1) is detachably connected with one end of a distribution beam (1), opposite-penetrating bolts used for being connected with the steel beam (4) are arranged on the other end of the distribution beam (1), the supporting rods (2-4) are arranged between the weight platform (2-3) and the distribution beam (1) in a detachable mode, the steel beam (4) stretches across a lighting top opening (5) and is conveyed to a required installation position through sliding units arranged at two ends of the steel beam (4).
- 2. The sliding device for installing the roof large-span daylighting roof steel girder according to claim 1, wherein each main frame (2-1) is welded into a whole by adopting four section steels, and the section steels are H-shaped steels, I-shaped steels, square steel pipes or channel steels.
- 3. The slippage device for the installation of roof large-span daylighting roof steel beams according to claim 1, wherein a universal wheel which is convenient to move is arranged at the bottom of each main frame (2-1).
- 4. The sliding device for installing the roof large-span daylighting roof steel girder according to claim 1, wherein the connecting rod (2-2) adopts H-shaped steel, I-shaped steel, square steel pipes or channel steel.
- 5. The sliding device for installing the roof large-span daylighting roof steel girder according to claim 1, wherein the main frame (2-1) and the connecting rod (2-2) are connected by bolts or pin shafts.
- 6. The sliding device for installing the roof large-span daylighting roof steel girder according to claim 1, wherein the supporting rods (2-4) are vertically arranged between the ballast platform (2-3) and the distribution beam (1), and two ends of the supporting rods (2-4) are respectively connected with the ballast platform (2-3) and the distribution beam (1) through bolts or pin shafts.
- 7. The sliding device for installing the roof large-span daylighting roof steel girder according to claim 1, wherein the lower flange of the distribution beam (1) is detachably connected with the top of the main frame (2-1) in the sliding structure (2) through a plurality of bolts.
- 8. The sliding device for installing the roof large-span daylighting roof steel girder according to claim 1, wherein the counterweight (3) adopts a poured counterweight water tank or counterweight.
- 9. The sliding device for installing the roof large-span daylighting roof steel girder according to claim 1, wherein the weight platform (2-3) is welded into a plane for placing the weight (3) by adopting a plurality of section steels, and the section steels are H-shaped steels, I-shaped steels, square steel pipes or channel steels.
Description
Sliding device for installing roof large-span daylighting roof steel girder Technical Field The utility model belongs to the field of construction equipment, and particularly relates to a sliding device for installing a roof large-span daylighting roof steel beam. Background In large-scale buildings, steel structures are mostly adopted for the design of roof daylighting roofs, and the roof daylighting roof has the advantages of large span, convenience in installation, rapidness in construction, light self weight of the structure and the like. However, the installation of the large-span daylighting roof girder cannot be carried out in a whole root for hoisting due to the limitation of the position and the span. The traditional construction method mostly adopts a bracket method, namely a support frame is arranged at the subsection position of the steel beam, and the steel beam is hoisted in a subsection manner. The support method has the limitations that (1) the construction period is prolonged due to the long construction period for erecting and dismantling the support frame. (2) Most of the lighting roof is an atrium space below, and the height of the support frame is higher, so that the measure cost is obviously increased. (3) In some cases, the tower crane or the large-sized automobile crane has higher use cost, and particularly when the daylighting roof steel beam is positioned in the center of a building, the hoisting operation radius is larger, and heavy equipment support is needed, so that the construction cost is further increased. It is therefore desirable to provide an apparatus for installation of roof large span roof girder steel. Disclosure of utility model The utility model aims to solve the defects in the prior art and provides a sliding device for installing a roof large-span daylighting roof steel beam. The device not only reduces the dependence on large-scale hoisting equipment, but also obviously reduces the construction cost and the construction period. The specific technical scheme adopted by the utility model is as follows: the utility model provides a sliding device for installing a roof large-span daylighting roof steel beam, which comprises two sliding units for moving the steel beam, wherein each sliding unit comprises a distribution beam, a sliding structure and a counterweight; The sliding structure comprises two main frames, connecting rods, a weight platform and supporting rods, wherein the two main frames are arranged in parallel at intervals, a detachable connecting rod is vertically arranged between the two main frames, the weight platform for placing a weight piece is arranged on one side of the main frames, the top of the main frames is detachably connected with one end of a distribution beam, the other end of the distribution beam is provided with a through bolt for connecting with a steel beam, the supporting rods are arranged between the weight platform and the distribution beam in a detachable mode, the steel beam stretches across a lighting roof hole, and the steel beam is conveyed to a required installation position through sliding units arranged at two ends of the steel beam. Preferably, each main frame is welded into a whole by adopting four section steels, and the section steels are H-shaped steels, I-shaped steels, square steel pipes or channel steels. Preferably, a universal wheel which is convenient to move is arranged at the bottom of each main frame. Preferably, the connecting rod adopts H-shaped steel, I-shaped steel, square steel pipes or channel steel. Preferably, the main frame and the connecting rod are connected by bolts or pin shafts. Preferably, the supporting rods are vertically arranged between the weighting platform and the distribution beam, and two ends of the supporting rods are respectively connected with the weighting platform and the distribution beam through bolts or pin shafts. Preferably, the lower flange of the distribution beam is detachably connected with the top of the main frame in the sliding structure through a plurality of bolts. Preferably, the weight piece adopts a water filled weight water tank or a weight block. Preferably, the weighting platform is welded into a plane for placing the weight by adopting a plurality of section steels, and the section steels are H-shaped steels, I-shaped steels, square steel pipes or channel steels. Compared with the prior art, the utility model has the following beneficial effects: The utility model provides a sliding device for installing a roof large-span daylighting roof steel girder. The sliding device comprises two sliding units arranged at two ends of the steel beam. The bottom of the sliding unit is provided with universal wheels which are convenient for the integral movement of the equipment and the steel beam, the top of the sliding unit is provided with a distribution beam, one end of the distribution beam is connected with the steel beam in a form of a through bolt, and the other end o