The utility model provides a post-pouring strip concrete template structure which comprises a prefabricated reinforced concrete template, a plurality of screws, a water stop sheet and a water stop sheet, wherein one end of each screw is connected with the same surface of the prefabricated reinforced concrete template, the other end of each screw is used for penetrating through a conventional template, and the water stop sheet is arranged in the middle of each screw. According to the post-pouring strip concrete template structure, the prefabricated reinforced concrete templates are arranged, the plurality of screw rods are connected to the same surface of the prefabricated reinforced concrete templates, the prefabricated reinforced concrete templates can be prefabricated and completed, the site construction time is shortened, after the post-pouring strip concrete pouring is completed, the prefabricated reinforced concrete templates can be subjected to subsequent outer wall waterproof layer construction and backfilling construction without dismantling, namely, the node time of the backfilling procedure is shortened, a large amount of construction periods are saved, and the efficiency of post-pouring strip construction is improved.

Inventors

  • ZHANG YIQING
  • HAO JINBIAO
  • GONG WEI
  • HAN LEI
  • ZHANG GUOKUI
  • LIU YINGZHANG
  • ZHANG JIEYU
  • DUAN CHENLIANG
  • QIN BO
  • YANG TENG

Assignees

  • 山西机械化建设集团有限公司

Dates

Publication Date
20260512
Application Date
20250523

Claims (7)

  1. 1. The post-cast strip concrete template structure is characterized by comprising: Prefabricating reinforced concrete templates (3); One end of each screw (1) is connected with the same surface of the prefabricated reinforced concrete template (3), and the other end of each screw (1) is used for penetrating through the conventional template (4); the water stop sheet (2) is arranged in the middle of the screw (1); The sleeve (5) is provided with internal threads, and the sleeve (5) is pre-embedded on the prefabricated reinforced concrete template (3) and is used for being in threaded connection with one end of the screw rod (1).
  2. 2. The post-pouring strip concrete formwork structure according to claim 1, wherein the cross section of the water stop sheet (2) is quadrilateral, and the water stop sheet (2) is welded at the middle part of the screw rod (1).
  3. 3. The post-cast strip concrete template structure according to claim 1, wherein the number of the screws (1) is 3-10.
  4. 4. The post-cast strip concrete formwork structure according to claim 1, wherein two ends of the prefabricated reinforced concrete formwork (3) along the first direction are respectively provided with a first step (31) and a second step (32), and the first step (31) and the second step (32) are complementary.
  5. 5. The post-cast strip concrete formwork structure according to claim 1, further comprising a sealant applied in a gap between the sleeve (5) and the screw (1).
  6. 6. The post-pouring strip concrete formwork structure according to claim 1, wherein the cross section of the water stop sheet (2) is square, and the side length of the water stop sheet (2) is 100mm.
  7. 7. Post-cast strip concrete formwork structure according to claim 4, characterized in that the thickness of the first step (31) or the second step (32) is half the thickness of the prefabricated reinforced concrete formwork (3).

Description

Post-pouring strip concrete template structure Technical Field The utility model relates to the technical field of building templates, in particular to a post-pouring strip concrete template structure. Background The down-pass construction is a complex systematic engineering requiring a large number of templates in the construction of the main structure. The construction flow of the lower through channel has a time node requirement. In the prior art, after the last section of construction of two adjacent sections of main structures of a lower through channel is finished, the formwork supporting work of a post-cast strip can be carried out after waiting for 28 days, the post-cast strip construction is allowed to be carried out after the top plate concrete is poured for 45 days, the post-cast strip is maintained until the design strength requirement is met after the post-cast strip concrete is poured, and then the construction of an outer wall waterproof layer and the backfilling construction are sequentially carried out. The existing exterior wall template can be removed after the concrete inside the exterior wall template is hardened to reach the design strength, and the exterior wall waterproof layer construction and backfilling construction cannot be performed during the concrete hardening, so that the post-pouring strip construction efficiency is lower. Disclosure of utility model The present utility model aims to solve at least one of the technical problems in the related art to a certain extent. Therefore, the utility model aims to provide a post-pouring belt concrete template structure which can accelerate the backfilling progress of a building and improve the construction efficiency of the post-pouring belt. In order to achieve the above purpose, the present utility model provides a post-cast strip concrete form structure, comprising: prefabricating reinforced concrete templates; One end of each screw is connected with the same surface of the prefabricated reinforced concrete template, and the other end of each screw is used for penetrating through the conventional template; And the water stopping sheet is arranged in the middle of the screw rod. According to the post-pouring strip concrete template structure, the prefabricated reinforced concrete templates are arranged, the plurality of screw rods are connected to the same surface of the prefabricated reinforced concrete templates, the prefabricated reinforced concrete templates can be prefabricated and completed, the site construction time is shortened, after the post-pouring strip concrete pouring is completed, the prefabricated reinforced concrete templates can be subjected to subsequent outer wall waterproof layer construction and backfilling construction without dismantling, namely, the node time of the backfilling procedure is shortened, a large amount of construction periods are saved, and the efficiency of post-pouring strip construction is improved. According to one embodiment of the utility model, the concrete slab further comprises a sleeve, wherein the sleeve is provided with internal threads, and the sleeve is pre-embedded on the precast reinforced concrete formwork and is used for being in threaded connection with one end of the screw rod. According to one embodiment of the utility model, the cross section of the water stop sheet is quadrilateral, and the water stop sheet is welded at the middle part of the screw rod. According to one embodiment of the utility model, the number of the screws is 3-10. According to one embodiment of the utility model, two ends of the precast reinforced concrete template along the first direction are respectively provided with a first step and a second step, and the first step and the second step are complementary. According to one embodiment of the utility model, the screw further comprises a sealant applied in the gap between the sleeve and the screw. According to one embodiment of the utility model, the cross section of the water stop sheet is square, and the side length of the water stop sheet is 100mm. According to one embodiment of the utility model, the thickness of the first step or the second step is half the thickness of the precast reinforced concrete form. Additional aspects and advantages of the utility model will be set forth in part in the description which follows and, in part, will be obvious from the description, or may be learned by practice of the utility model. Drawings Various other advantages and benefits will become apparent to those of ordinary skill in the art upon reading the following detailed description of the preferred embodiments. The drawings are only for purposes of illustrating the preferred embodiments and are not to be construed as limiting the utility model. Also, like reference numerals are used to designate like parts throughout the figures. Wherein: Fig. 1 is a schematic structural view of a post-cast strip concrete form according to an embodiment of the present ut