JP-7854904-B2 - Information processing device, information processing method, and program

JP7854904B2JP 7854904 B2JP7854904 B2JP 7854904B2JP-7854904-B2

Inventors

  • 戸倉 健太郎
  • 相良 毅
  • 前田 茂隆
  • 松井 幸一郎
  • 帖佐 泰郎
  • 陣内 久之
  • 渡部 栄二
  • 白花 秀高

Assignees

  • 三井住友建設株式会社

Dates

Publication Date
20260507
Application Date
20220907

Claims (5)

  1. A construction overview registration unit registers the level of detail required for the work cost survey of the construction project and the identification information of the construction project in question into a construction overview database. A cost estimation data registration unit receives cost estimation data associated with the identification information of the aforementioned construction work and registers it in a cost estimation database, wherein the cost estimation data includes the quantity of materials used in the aforementioned construction work aggregated for each work item according to the level of detail, and the work item is set to include detailed work locations and/or construction methods as the level of detail increases , The subcontractor registration department receives information on the person in charge associated with the identification information of the aforementioned construction work and registers it in the subcontractor database. A notification unit that transmits information necessary for registering work performance to the person in charge based on the information of the person in charge, A transmission unit that transmits the level of detail associated with the identification information of the construction work to the server to which the employee's terminal connects when registering work results, A work performance import unit receives work performance data associated with the identification information of the aforementioned construction work from the server and registers it in a work performance database, wherein the work performance data includes the number of people and occupations for each work content of the work location and/or construction method, set according to the level of detail associated with the identification information of the aforementioned construction work transmitted by the transmission unit, and having the same level of detail as the cost estimation data associated with the identification information of the aforementioned construction work . Upon receiving identification information for the target construction project, a unit cost calculation unit calculates a unit cost for each work item based on the quantity for each work item related to the target construction project stored in the cost estimation database and the number of people for each work item related to the target construction project stored in the work performance database, expressed as the number of people × (work time performed by one worker in one day) / quantity . The unit comprises an output unit that outputs the results calculated by the unit cost calculation unit , The work performance acquisition unit is an information processing device that requests the notification unit to notify the person in charge if there is a discrepancy between the job title and the work content .
  2. The information processing apparatus according to claim 1 , wherein the work performance acquisition unit checks the work performance data, and if there are any deficiencies in the work performance data, requests the notification unit to notify the person in charge.
  3. The aforementioned construction overview registration unit further registers construction conditions that may affect the unit cost in the aforementioned construction overview database. The information processing device according to claim 1, wherein the output unit outputs the calculation results along with the construction conditions.
  4. A method executed by an information processing device that is connected to a server that the employee's terminal connects to when registering work results, The steps include: registering the level of detail required for the work cost survey of the construction project in the project overview database, associating it with the identification information of the project; A step of receiving cost estimation data associated with the identification information of the aforementioned construction work and registering it in a cost estimation database, wherein the cost estimation data includes the quantity of materials used in the construction work aggregated for each work item according to the level of detail , and the higher the level of detail, the more detailed the work items for the work location and/or construction method are set . The steps include receiving information on the person in charge associated with the identification information of the aforementioned construction work and registering it in the subcontractor database, The steps include: sending the information necessary for registering work performance to the person in charge based on the information of the person in charge; The steps include transmitting the level of detail associated with the identification information of the construction work to the server, A step of receiving work performance data associated with the identification information of the aforementioned construction work from the server and registering it in a work performance database, wherein the work performance data includes the number of people and occupations for each work content of the work location and/or construction method , set according to the level of detail associated with the identification information of the aforementioned construction work transmitted in the transmission step, and having the same level of detail as the cost estimation data associated with the identification information of the aforementioned construction work; A process to send a notification to the person in charge when there is a discrepancy between the job title and the work content, Upon receiving identification information for the target construction project, the process involves calculating a unit cost for each work item based on the quantity for each work item related to the target construction project stored in the cost estimation database and the number of people for each work item related to the target construction project stored in the work performance database, expressed as: number of people × (work time performed by one worker in one day) / quantity . A method that includes the step of outputting the calculated result.
  5. When the employee's terminal registers work performance, the information processing device is connected to the server and is able to communicate with it. A process to associate the level of detail required for a construction cost survey with the identification information of the construction project and register it in the construction summary database, A process for receiving cost estimation data associated with the identification information of the aforementioned construction work and registering it in a cost estimation database, wherein the cost estimation data includes the quantity of materials used in the construction work aggregated for each work item according to the level of detail , and the higher the level of detail, the more detailed the work items, including the work location and/or construction method, are set . The process involves receiving information on the person in charge associated with the identification information of the aforementioned construction work and registering it in the subcontractor database. Based on the information of the person in charge, the process involves sending the information necessary for registering work performance to the person in charge. The process of transmitting the level of detail associated with the identification information of the construction work to the server, A process for receiving work performance data associated with the identification information of the aforementioned construction work from the server and registering it in a work performance database, wherein the work performance data includes the number of people and occupations for each work content of the work location and/or construction method , set according to the level of detail associated with the identification information of the aforementioned construction work transmitted by the transmission process, and having the same level of detail as the cost estimation data associated with the identification information of the aforementioned construction work. A process to send a notification to the person in charge when there is a discrepancy between the job title and the work content, Upon receiving identification information for the target construction project, the system performs a process to calculate the unit cost for each work item, expressed as: number of workers × (work time per worker per day) / quantity, based on the quantity for each work item related to the target construction project stored in the cost estimation database and the number of workers for each work item related to the target construction project stored in the work performance database . A program that executes a process to output the calculated results.

Description

This invention relates to an information processing device, an information processing method, and a program. Unit costs are crucial data for estimating construction costs. Construction companies, as the main project managers, can calculate accurate budgets by using unit costs that match the work performance of each subcontractor. Traditionally, collecting unit cost data required construction companies to expedite considerable effort, such as sending surveyors to the site to investigate daily performance for each type of work, or organizing and compiling daily reports for each type of work. Progress management systems for appropriate progress control at construction sites have been proposed and put into practical use. Patent Document 1 discloses a progress management method that identifies the next process and notifies the workers in that process with work instructions, thereby enabling workers in each process to perform their tasks efficiently in a project consisting of multiple processes. Japanese Patent Publication No. 2005-267523 This figure shows an example of the configuration of a cost survey system according to one embodiment of the present invention.This figure shows an example of the configuration of a server device according to one embodiment of the present invention.This figure shows an example of the configuration of an administrator terminal related to one embodiment of the present invention.This figure shows an example of the configuration of a daily report server related to one embodiment of the present invention.This figure shows an example of the hardware configuration of a server device according to one embodiment of the present invention.This figure shows an example of the hardware configuration of an administrator terminal according to one embodiment of the present invention.This figure shows an example of a construction project overview database related to one embodiment of the present invention.This figure shows an example of a partner company database according to one embodiment of the present invention.This figure shows an example of an estimation database related to one embodiment of the present invention.This is a flowchart illustrating the processing of a server device according to one embodiment of the present invention.This flowchart illustrates the processing of a daily report server in one embodiment of the present invention.This figure shows an example of a work performance registration screen according to one embodiment of the present invention. The embodiments of the present invention will be described with reference to the attached drawings. The following embodiments are provided to facilitate understanding of the present invention and are not intended to limit its interpretation. Furthermore, the present invention can be modified in various ways without departing from its essence. Those skilled in the art can also adopt embodiments in which each of the elements described below is replaced with equivalent components, and such embodiments are also included within the scope of the present invention. (System configuration) First, the outline of the present invention will be explained using Figure 1. Figure 1 is a diagram illustrating the configuration of a work rate survey system according to one embodiment of the present invention. The work rate survey system 1 includes a server device 10, and the server device 10 is configured to communicate with an administrator terminal 20, a staff terminal 30, and a daily report server 40 via a network N. The work rate survey system 1 is a system capable of acquiring accurate work rate data after the completion of work. The administrator of the work rate survey system 1 can connect to the server device 10 via the administrator terminal 20 and save various data necessary for the work rate survey. Specifically, the administrator can use the administrator terminal 20 to save information on the construction project to be surveyed into the project overview database. Furthermore, the administrator can use the administrator terminal 20 to register the on-site personnel responsible for the construction project to be surveyed, associating them with the project overview. The administrator can also use the administrator terminal 20 to save the cost estimation data for the construction project being investigated to the cost estimation database. The cost estimation data includes the quantities of materials used in the construction, aggregated according to the level of detail of the work unit survey. Level of detail refers to information indicating the level of detail in the work unit survey; in this embodiment, information of "high," "medium," or "low" is stored according to the importance of the construction project. Work content refers to information indicating the work location and/or construction method. For example, if the importance of the construction is standard and a "medium" level of detail survey is required, the materials used in the cons