JP-7855909-B2 - Process control support system, process control support method, and program
Inventors
- 池田 雄一
- 本谷 淳
- 塩坂 靖彦
- ▲濱▼村 明子
Assignees
- 株式会社大林組
Dates
- Publication Date
- 20260511
- Application Date
- 20220421
Claims (9)
- A process management support system that assists in the process management of construction work, A model acquisition unit that acquires element models corresponding to the construction members constituting the structure from a three-dimensional shape model of the structure, A data acquisition unit that acquires 3D point cloud data generated by surveying the aforementioned structure under construction, A frame creation unit that creates a determination frame corresponding to the construction member based on the element model or a bounding box circumscribing the element model, A completion determination unit overlays the three-dimensional point cloud data with the element model or the determination frame to determine whether the construction is complete or incomplete for each corresponding construction member . A process control support system characterized by comprising the following features.
- In the process control support system according to claim 1, The completion determination unit When a number of three-dimensional point cloud data exceeding a predetermined threshold is detected within the internal region of the element model or the determination frame , A process management support system characterized by determining that the construction member corresponding to the element model is complete.
- In the process control support system according to claim 1, A process management support system characterized by comprising a completion information output unit that reflects the information acquired by the completion determination unit into the element model and outputs it.
- In the process control support system according to claim 1, The model extraction unit extracts the element model corresponding to the construction member selected as the target for determination from the element models acquired by the model acquisition unit, The completion determination unit is characterized by overlaying the three-dimensional point cloud data with the element model extracted by the model extraction unit, thereby providing a process control support system.
- In the process control support system according to claim 1 , A process control support system characterized in that the determination frame comprises an outer shell formed by enlarging or reducing the element model or the bounding box.
- In the process control support system according to claim 1 , A process control support system characterized in that the determination frame comprises an outer shell formed by enlarging the element model or the bounding box and an inner shell formed by reducing the element model or bounding box.
- In the process control support system according to claim 1, The three-dimensional shape model of the aforementioned structure is a BIM model, A process control support system characterized in that the element model is a component that constitutes the BIM model.
- There are process management support methods that assist in the process management of construction work, Computers A step of obtaining element models corresponding to multiple construction members constituting the structure from a three-dimensional shape model of the structure, A process of obtaining 3D point cloud data generated by surveying the aforementioned structure under construction, A step of creating a determination frame corresponding to the construction member based on the element model or a bounding box circumscribing the element model, A step of determining whether construction is complete or incomplete for each corresponding construction member by superimposing the aforementioned element model or the aforementioned determination frame with the aforementioned 3D point cloud data, A method for supporting the process management of construction work, characterized by performing the following.
- A step of obtaining element models corresponding to multiple construction members constituting the structure from a three-dimensional shape model of the structure, A process of obtaining 3D point cloud data generated by surveying the aforementioned structure under construction, A step of creating a determination frame corresponding to the construction member based on the element model or a bounding box circumscribing the element model, A step of determining whether construction is complete or incomplete for each corresponding construction member by superimposing the aforementioned element model or the aforementioned determination frame with the aforementioned 3D point cloud data, A program characterized by causing a computer to execute something.
Description
This invention relates to a process management support system, a process management support method, and a program for understanding and managing the progress of construction work at a construction site. In construction sites, the progress of construction is often managed by compiling records from construction managers and reports from specialized contractors, which is a cumbersome process and presents challenges in information sharing. In this context, for example, Patent Document 1 discloses a building construction management system that supports building construction management. In the construction management system described in Patent Document 1, information such as the name, location, and shape of each component constituting the building is imported and set from, for example, BIM (Building Information Modeling) software that allows for the three-dimensional design of the building in a virtual space. Furthermore, information such as the construction cost, planned start date, planned completion date, actual start date, and actual completion date for each component constituting the building is imported and set from software that supports the construction process management of the building. This allows for the three-dimensional, visual display of components that have been completed, are progressing smoothly, are ahead of schedule, and are behind schedule, based on a predetermined reference date, using BIM software. Patent No. 6876523 This figure shows the BIM model and element model in an embodiment of the present invention.This figure shows the surveying means in an embodiment of the present invention.This figure shows a schematic of the three-dimensional point cloud data in an embodiment of the present invention.This figure shows a bounding box and a determination frame in an embodiment of the present invention.This diagram shows the flow of a process control support method according to an embodiment of the present invention.This figure shows a process control support system according to an embodiment of the present invention.This figure shows the element model of the construction section set as the target for construction determination in an embodiment of the present invention.This figure shows an example of displaying the construction determination result in a BIM model according to an embodiment of the present invention.This diagram shows the stages of distribution of construction materials in the construction of a structure. <<<<Distribution of construction materials>>>> Construction components E used in the construction of building B are manufactured at factory f1, as shown in Figure 9, and stored in the storage area of factory f1. Then, the construction components E are loaded onto a freight car v1 and transported from factory f1 to the construction site f2. After the construction components E are brought to the construction site f2, they are temporarily stored in the stockyard of the construction site f2. Next, the construction components E stored in the stockyard are transported to the work yard where construction will take place. If necessary, multiple construction components E are assembled in the work yard. Then, using a tower crane or similar equipment, they are lifted from the work yard and the construction components E are installed (erected). Afterward, the construction components M used in the erection of building B are inspected. <<<Process Management Support System and Process Management Support Method>>> The process management support system and process management support method automatically determine whether the erection of construction components E at the distribution stage, as described above, is completed or incomplete, and supports the process management of construction work. The details of the process management support system and process management support method will be explained below with reference to Figures 1 to 8. The automatic determination of whether construction is complete or incomplete utilizes a 3D geometric model of the structure, which is constructed on a computer before construction, and 3D point cloud data generated by surveying the structure during construction. While there are no limitations on the method of constructing the 3D geometric model, this embodiment uses a Building Information Modeling (BIM) model as an example. First, we will explain the BIM model 10, element model 11, 3D point cloud data D, bounding box 40, and judgment frame 41 used in the process control support system and process control support method. <<<BIM Model / Element Model>>> As shown in Figure 1, the BIM model 10 is a three-dimensional model of the actual building B constructed on a computer using BIM software. The three-dimensional geometric element models 11, which are components of the BIM model 10, are three-dimensional models of the actual construction members E that make up building B. The element models 11 are assigned attribute information, placement information, and shape info