The present invention relates to a set of movable platforms for inspecting internal pipe equipment. It comprises a rectangular work platform installed to rest on a set of steel pipes placed on the inner floor of the pipe to support the work platform during the inspection of equipment constructed inside the pipe; handrails assembled and installed on both sides of the rectangular work platform to guide the movement of workers and prevent safety accidents during the internal inspection of the pipe; and an arc-shaped pipe flange fixing plate formed and attached to one end of the rectangular work platform so as to be fastened with a fixing bolt to the pipe flange at the entrance to concentrate the arrangement of the set of steel pipes and prevent movement of the rectangular work platform. By installing and using a movable platform that fits the diameter of the pipe during the inspection of internal pipe equipment, it is possible to induce smooth entry of workers into the pipe and secure sufficient workspace. Furthermore, by providing disassemblable handrails on both sides of the work platform, it is possible to prevent industrial accidents such as falls during work and slip accidents during the installation of steel pipe scaffolding, thereby improving work efficiency.

Inventors

  • 김권
  • 김영준

Assignees

  • 한전케이피에스 주식회사

Dates

Publication Date
20260511
Application Date
20240920

Claims (8)

  1. delete
  2. A set of movable platforms for inspecting equipment inside a pipe comprises: a rectangular work platform (40) installed on a set of steel pipes (20) placed on the inner floor of the pipe to support the work platform during equipment inspection inside the pipe (4); hand rails (60) assembled and installed on both sides of the rectangular work platform (40) to guide the movement of workers and prevent safety accidents during internal inspection of the pipe (4); and an arc-shaped pipe flange fixing plate (80) formed attached to one end of the rectangular work platform (40) so that it can be fastened with a fixing bolt to the pipe flange (6) at the entrance to concentrate the arrangement of the set of steel pipes (20) and prevent movement of the rectangular work platform (40). The above set steel pipe (20) is, It is formed to be longer than the rectangular work platform (40), A movable stepping plate set for inspecting internal pipe equipment, characterized by being formed by being attached to each other so that they can be inserted and installed in a three-row arrangement inside a pipe seating groove (84) formed in an arc-shaped pipe flange fixing plate (80).
  3. In Article 2, The above rectangular work platform (40) is, A check plate (44) formed to be used as a step inside the pipe, and A movable stepping plate set for inspecting internal pipe equipment, characterized by comprising an insertion section (48) formed by attaching a handrail fixing bolt (46) that can be tightened and loosened so that a handrail (60) can be assembled and installed on both longitudinal sides of a check plate (44).
  4. In Paragraph 3, On the above rectangular work platform (40), A movable stepping stool set for inspecting internal pipe equipment, characterized by being formed by further forming a rectangular support frame having a certain thickness and length on the bottom surface of a check plate (44) used as a stepping stool inside a pipe (4).
  5. In Paragraph 3, The above rectangular work platform (40) is It is formed with a check plate (44), A movable platform set for inspecting internal pipe equipment, characterized by being connected by hinges (47) between check plates (44) so that the length can be extended by connecting additional check plates (44) to one end of the check plate (44), the check plates (44) can be unfolded when installing the work platform (40), and the check plates (44) can be folded when storing the work platform (40).
  6. In Article 2, The above handrail (60) is, A horizontal guide bar (62) formed horizontally at a certain height and in a rectangular shape so as to be used as a handle while moving on a work platform (40), and A movable stepping plate set for inspecting internal pipe equipment, characterized in that the horizontal guide bar (62) is formed at a certain height and has a certain length at a certain interval on the horizontal guide bar (62), and is formed with a vertical support bar (64) formed with a thickness that allows for disassembly and assembly on the insertion pipe (48).
  7. In Article 2, The above arc-shaped pipe flange fixing plate (80) is, It is formed vertically attached to one end of the check plate (44) of the rectangular work platform (40) and formed in an arc shape so as to correspond to the pipe flange (6), A pipe seating groove (84) formed in a certain shape at the center so that it can be tightly seated on the upper part of the set steel pipe (20), and A movable stepping plate set for inspecting internal pipe equipment, characterized by including a fastening plate (88) formed in a certain shape so as to be fastened with a fixing bolt to a plurality of fastening holes (86) drilled on both sides of the pipe seating groove (84) so as to correspond to the bolt holes (8) of the pipe flange (6).
  8. In Article 2, The above rectangular work platform (40) is, A set of movable platforms for inspecting equipment inside a pipe, characterized by being firmly fixed to the pipe flange (6) by an arc-shaped pipe flange fixing plate (80) that prevents slipping and falls when the set steel pipe (20) is installed as scaffolding during equipment inspection inside the pipe (4).

Description

Transfer platform set for inspecting inside equipment of plumbing The present invention relates to a set of movable platforms for inspecting internal pipe equipment. Specifically, the invention relates to a set of movable platforms for inspecting internal pipe equipment that improves work efficiency by preventing industrial accidents such as falls during work and slipping accidents when installing steel pipe scaffolding, by installing and using a movable platform that fits the diameter of the pipe during the inspection of internal pipe equipment, thereby facilitating smooth entry of a worker into the pipe and securing sufficient workspace, while also being equipped with detachable and assembleable handrails on both sides of the platform. Generally, "spanning platform for inspecting internal piping equipment" is a widely disclosed item, so a detailed description is omitted; however, reference may be made to Published Utility Model No. 20-2023-0001209 "Multipurpose work safety platform" and Registered Patent No. 10-2100383 "System scaffolding for inspecting internal piping," etc. Meanwhile, the aforementioned "multi-purpose work safety platform" is designed to be installed using beams or pipes that constitute the piping or supports of a workspace where the gas turbine's intake air filter is installed; however, since it is used as an inspection platform utilizing steel pipe scaffolding, there are problems such as a narrow width due to the diameter limitation of the entrance and the risk of industrial accidents caused by falling and slipping during work at height. Furthermore, although the aforementioned “system scaffolding for internal pipe inspection” is designed to improve work efficiency and ensure safe operation by standardizing installation and dismantling to reduce manpower and time and lower costs, it is limited to inclined supports installed on the inner walls of inclined pipes. Consequently, when steel pipe scaffolding is used as an inspection platform, there are problems such as a narrow width due to the limited diameter of the entry point, and a risk of industrial accidents caused by falls and slipping during work at heights. Meanwhile, since steel pipe scaffolding is generally used as an inspection platform when workers enter the pipe to perform work during equipment inspections installed inside the pipe, there is a problem in that the entry point is narrow due to diameter limitations, and there is a risk of industrial accidents caused by falls and slips during work at heights. FIGS. 1a), 1b), and 1c) are drawings illustrating a set of movable platforms for inspecting internal piping equipment according to the present invention. FIG. 2 is a schematic drawing showing the installation inside the piping of the movable platform shown in FIG. 1. FIGS. 3a)b) is a schematic drawing showing the front and side of the movable platform shown in FIG. 2. FIG. 4 is a plan view schematically illustrating a work platform on a movable platform shown in FIG. 2. To fully understand the present invention, preferred embodiments of the invention will be described with reference to the accompanying drawings. Embodiments of the present invention may be modified in various forms, and the scope of the present invention should not be interpreted as being limited to the embodiments described in detail below. These embodiments are provided to more completely explain the present invention to those with average knowledge in the art. Accordingly, the shapes of elements in the drawings may be exaggerated to emphasize clearer explanations. It should be noted that in each drawing, identical components may be depicted with the same reference numerals. Furthermore, detailed descriptions of known functions and configurations that are deemed to unnecessarily obscure the essence of the present invention are omitted. Hereinafter, a movable platform set for inspecting internal piping equipment according to the present invention will be described in detail by explaining a preferred embodiment of the present invention with reference to the attached drawings. The movable platform set (2) for inspecting internal pipe equipment according to the present invention comprises, as shown in FIGS. 1 to 3, a rectangular work platform (40) installed by being placed on a set steel pipe (20) placed on the inner floor of the pipe to support the work platform when inspecting equipment built inside the pipe (4); hand rails (60) assembled and installed on both sides of the rectangular work platform (40) to guide the movement of the worker and prevent safety accidents when inspecting the inside of the pipe (4); and an arc-shaped pipe flange fixing plate (80) formed attached to one end of the rectangular work platform (40) so that it can be fastened with a fixing bolt to the pipe flange (6) at the entrance to concentrate the arrangement of the set steel pipes (20) and prevent movement of the rectangular work platform (40). In addition, as shown in FIGS. 1 to 3,